05/15/2018 OHARE MODERNIZATION PROJECT $9,345,000.00

Modifications/Amendments

Modification # Description Disclosure # Award Date Start Date End Date Department Amount
CENTRAL DEICING FACILITY (CDF) - RAMP TOWER 10/16/2018 OHARE MODERNIZATION PROJECT $4,481.00
CENTRAL DEICING FACILITY (CDF) - RAMP TOWER 02/26/2019 OHARE MODERNIZATION PROJECT $6,038.00
CENTRAL DEICING FACILITY (CDF) - RAMP TOWER 03/06/2019 OHARE MODERNIZATION PROJECT $1,982.00
CENTRAL DEICING FACILITY (CDF) - RAMP TOWER 03/08/2019 OHARE MODERNIZATION PROJECT $192,449.00
CENTRAL DEICING FACILITY (CDF) - RAMP TOWER 03/12/2019 OHARE MODERNIZATION PROJECT $1,605.00
7592314
CENTRAL DEICING FACILITY (CDF) - RAMP TOWER 03/15/2019 OHARE MODERNIZATION PROJECT $136,754.00
7592315
CENTRAL DEICING FACILITY (CDF) - RAMP TOWER 03/21/2019 OHARE MODERNIZATION PROJECT $12,884.00
7592316
CENTRAL DEICING FACILITY (CDF) - RAMP TOWER 03/22/2019 OHARE MODERNIZATION PROJECT $47,677.00
7592317
CENTRAL DEICING FACILITY (CDF) - RAMP TOWER 04/11/2019 OHARE MODERNIZATION PROJECT $1,727.00
7592318
CENTRAL DEICING FACILITY (CDF) - RAMP TOWER 04/12/2019 OHARE MODERNIZATION PROJECT $5,024.00
CENTRAL DEICING FACILITY (CDF) - RAMP TOWER 10/17/2018 OHARE MODERNIZATION PROJECT $2,430.00
7592320
CENTRAL DEICING FACILITY (CDF) - RAMP TOWER 05/16/2019 OHARE MODERNIZATION PROJECT $3,592.00
7592321
CENTRAL DEICING FACILITY (CDF) - RAMP TOWER 05/17/2019 OHARE MODERNIZATION PROJECT $34,266.00
7592322
CENTRAL DEICING FACILITY (CDF) - RAMP TOWER 07/02/2019 OHARE MODERNIZATION PROJECT ($912,160.29)
7592323
CENTRAL DEICING FACILITY (CDF) - RAMP TOWER 10/04/2019 OHARE MODERNIZATION PROJECT ($348,586.82)
7592324
CENTRAL DEICING FACILITY (CDF) - RAMP TOWER 10/04/2019 OHARE MODERNIZATION PROJECT $56,060.00
CENTRAL DEICING FACILITY (CDF) - RAMP TOWER 12/20/2018 OHARE MODERNIZATION PROJECT $130,000.00
CENTRAL DEICING FACILITY (CDF) - RAMP TOWER 01/15/2019 OHARE MODERNIZATION PROJECT $132,575.00
CENTRAL DEICING FACILITY (CDF) - RAMP TOWER 01/30/2019 OHARE MODERNIZATION PROJECT $42,070.00
CENTRAL DEICING FACILITY (CDF) - RAMP TOWER 02/01/2019 OHARE MODERNIZATION PROJECT $16,897.00
CENTRAL DEICING FACILITY (CDF) - RAMP TOWER 02/21/2019 OHARE MODERNIZATION PROJECT ($160,917.00)
CENTRAL DEICING FACILITY (CDF) - RAMP TOWER 02/21/2019 OHARE MODERNIZATION PROJECT $95,820.00
CENTRAL DEICING FACILITY (CDF) - RAMP TOWER 02/22/2019 OHARE MODERNIZATION PROJECT $2,477.00