Modification # | Description | Disclosure # | Award Date | Start Date | End Date | Amount |
---|---|---|---|---|---|---|
7553210
| DWM Sewer Improvement Project Package P-2017-08 - Various Locations | 05/27/2020 | $206,255.52 | |||
DWM Sewer Improvement Project Package P-2017-08 - Various Locations | 06/09/2020 | $263,000.00 | ||||
DWM Sewer Improvement Project Package P-2017-08 - Various Locations | 12/04/2019 | $26,000.00 | ||||
DWM Sewer Improvement Project Package P-2017-08 - Various Locations | 12/18/2019 | $273,776.31 | ||||
755325
| DWM Sewer Improvement Project Package P-2017-08 - Various Locations | 02/10/2020 | ($631,393.95) | |||
755326
| DWM Sewer Improvement Project Package P-2017-08 - Various Locations | 03/09/2020 | $206,255.23 | |||
755329
| DWM Sewer Improvement Project Package P-2017-08 - Various Locations | 05/21/2020 | $0.01 |