Contract (PO) # Disclosure # Award Date Start Date End Date Department Original Award Amount
12/15/2009 CHICAGO DEPARTMENT OF TRANSPORTATION $25,257,000.00

Modifications/Amendments

Modification # Description Disclosure # Award Date Start Date End Date Department Amount
MORGAN STREET ELEVATED STATION PROJECT 07/13/2010 CHICAGO DEPARTMENT OF TRANSPORTATION $50,000.00
MORGAN STREET ELEVATED STATION PROJECT 08/16/2011 CHICAGO DEPARTMENT OF TRANSPORTATION $5,000.00
2119011
MORGAN STREET ELEVATED STATION PROJECT 11/22/2011 CHICAGO DEPARTMENT OF TRANSPORTATION $1,106,572.84
2119012
MORGAN STREET ELEVATED STATION PROJECT 11/29/2011 CHICAGO DEPARTMENT OF TRANSPORTATION $50,000.00
2119013
MORGAN STREET ELEVATED STATION PROJECT 02/28/2012 CHICAGO DEPARTMENT OF TRANSPORTATION $50,000.00
2119014
MORGAN STREET ELEVATED STATION PROJECT 03/08/2012 CHICAGO DEPARTMENT OF TRANSPORTATION $50,000.00
MORGAN STREET ELEVATED STATION PROJECT 03/12/2012 CHICAGO DEPARTMENT OF TRANSPORTATION $20,000.00
2119016
MORGAN STREET ELEVATED STATION PROJECT 04/03/2012 CHICAGO DEPARTMENT OF TRANSPORTATION $91,511.00
2119017
MORGAN STREET ELEVATED STATION PROJECT 04/27/2012 CHICAGO DEPARTMENT OF TRANSPORTATION $50,000.00
2119018
MORGAN STREET ELEVATED STATION PROJECT 06/13/2012 CHICAGO DEPARTMENT OF TRANSPORTATION $100,000.00
MORGAN STREET ELEVATED STATION PROJECT 07/16/2012 CHICAGO DEPARTMENT OF TRANSPORTATION $21,000.00
MORGAN STREET ELEVATED STATION PROJECT 10/08/2010 CHICAGO DEPARTMENT OF TRANSPORTATION $190,000.00
MORGAN STREET ELEVATED STATION PROJECT 07/17/2012 CHICAGO DEPARTMENT OF TRANSPORTATION $108,000.00
MORGAN STREET ELEVATED STATION PROJECT 07/26/2012 CHICAGO DEPARTMENT OF TRANSPORTATION $5,302.50
MORGAN STREET ELEVATED STATION PROJECT 07/30/2012 CHICAGO DEPARTMENT OF TRANSPORTATION $30,000.00
MORGAN STREET ELEVATED STATION PROJECT 07/31/2012 CHICAGO DEPARTMENT OF TRANSPORTATION $55,000.00
MORGAN STREET ELEVATED STATION PROJECT 08/02/2012 CHICAGO DEPARTMENT OF TRANSPORTATION $75,000.00
MORGAN STREET ELEVATED STATION PROJECT 08/06/2012 CHICAGO DEPARTMENT OF TRANSPORTATION $98,000.00
MORGAN STREET ELEVATED STATION PROJECT 08/08/2012 CHICAGO DEPARTMENT OF TRANSPORTATION $97,500.00
MORGAN STREET ELEVATED STATION PROJECT 08/08/2012 CHICAGO DEPARTMENT OF TRANSPORTATION $18,000.00
MORGAN STREET ELEVATED STATION PROJECT 08/10/2012 CHICAGO DEPARTMENT OF TRANSPORTATION ($6,878.08)
MORGAN STREET ELEVATED STATION PROJECT 08/14/2012 CHICAGO DEPARTMENT OF TRANSPORTATION $32,923.55
MORGAN STREET ELEVATED STATION PROJECT 01/13/2011 CHICAGO DEPARTMENT OF TRANSPORTATION $95,000.00
MORGAN STREET ELEVATED STATION PROJECT 08/17/2012 CHICAGO DEPARTMENT OF TRANSPORTATION ($7,882.28)
MORGAN STREET ELEVATED STATION PROJECT 08/27/2012 CHICAGO DEPARTMENT OF TRANSPORTATION $62,000.00
MORGAN STREET ELEVATED STATION PROJECT 08/28/2012 CHICAGO DEPARTMENT OF TRANSPORTATION $91,000.00
MORGAN STREET ELEVATED STATION PROJECT 08/30/2012 CHICAGO DEPARTMENT OF TRANSPORTATION $50,000.00
MORGAN STREET ELEVATED STATION PROJECT 08/31/2012 CHICAGO DEPARTMENT OF TRANSPORTATION ($4,684.67)
MORGAN STREET ELEVATED STATION PROJECT 08/31/2012 CHICAGO DEPARTMENT OF TRANSPORTATION ($17,081.29)
MORGAN STREET ELEVATED STATION PROJECT 09/05/2012 CHICAGO DEPARTMENT OF TRANSPORTATION ($174.72)
MORGAN STREET ELEVATED STATION PROJECT 09/05/2012 CHICAGO DEPARTMENT OF TRANSPORTATION $34,700.00
MORGAN STREET ELEVATED STATION PROJECT 09/07/2012 CHICAGO DEPARTMENT OF TRANSPORTATION ($17,502.37)
MORGAN STREET ELEVATED STATION PROJECT 09/10/2012 CHICAGO DEPARTMENT OF TRANSPORTATION ($16,929.35)
MORGAN STREET ELEVATED STATION PROJECT 03/11/2011 CHICAGO DEPARTMENT OF TRANSPORTATION $18,000.00
MORGAN STREET ELEVATED STATION PROJECT 09/12/2012 CHICAGO DEPARTMENT OF TRANSPORTATION $28,000.00
MORGAN STREET ELEVATED STATION PROJECT 09/13/2012 CHICAGO DEPARTMENT OF TRANSPORTATION ($26,419.53)
2119042
MORGAN STREET ELEVATED STATION PROJECT 09/17/2012 CHICAGO DEPARTMENT OF TRANSPORTATION $100,000.00
MORGAN STREET ELEVATED STATION PROJECT 09/19/2012 CHICAGO DEPARTMENT OF TRANSPORTATION $46,000.00
MORGAN STREET ELEVATED STATION PROJECT 09/21/2012 CHICAGO DEPARTMENT OF TRANSPORTATION $11,848.29
MORGAN STREET ELEVATED STATION PROJECT 09/25/2012 CHICAGO DEPARTMENT OF TRANSPORTATION $35,000.00
MORGAN STREET ELEVATED STATION PROJECT 09/26/2012 CHICAGO DEPARTMENT OF TRANSPORTATION ($126.97)
MORGAN STREET ELEVATED STATION PROJECT 11/01/2012 CHICAGO DEPARTMENT OF TRANSPORTATION $98,000.00
MORGAN STREET ELEVATED STATION PROJECT 11/28/2012 CHICAGO DEPARTMENT OF TRANSPORTATION ($18,928.91)
MORGAN STREET ELEVATED STATION PROJECT 11/30/2012 CHICAGO DEPARTMENT OF TRANSPORTATION $11,472.08
MORGAN STREET ELEVATED STATION PROJECT 12/06/2012 CHICAGO DEPARTMENT OF TRANSPORTATION $3,629.48
MORGAN STREET ELEVATED STATION PROJECT 12/07/2012 CHICAGO DEPARTMENT OF TRANSPORTATION $5,574.63
MORGAN STREET ELEVATED STATION PROJECT 12/10/2012 CHICAGO DEPARTMENT OF TRANSPORTATION $9,420.36
MORGAN STREET ELEVATED STATION PROJECT 12/11/2012 CHICAGO DEPARTMENT OF TRANSPORTATION $7,443.45
MORGAN STREET ELEVATED STATION PROJECT 12/13/2012 CHICAGO DEPARTMENT OF TRANSPORTATION $4,585.08
2119055
MORGAN STREET ELEVATED STATION PROJECT 01/03/2013 CHICAGO DEPARTMENT OF TRANSPORTATION $100,000.00
MORGAN STREET ELEVATED STATION PROJECT 01/29/2013 CHICAGO DEPARTMENT OF TRANSPORTATION $97,000.00
MORGAN STREET ELEVATED STATION PROJECT 02/13/2013 CHICAGO DEPARTMENT OF TRANSPORTATION $40,000.00
MORGAN STREET ELEVATED STATION PROJECT 04/30/2013 CHICAGO DEPARTMENT OF TRANSPORTATION ($28,539.05)
MORGAN STREET ELEVATED STATION PROJECT 05/16/2013 CHICAGO DEPARTMENT OF TRANSPORTATION ($14,721.88)
MORGAN STREET ELEVATED STATION PROJECT 06/21/2011 CHICAGO DEPARTMENT OF TRANSPORTATION $35,931.29
2119060
MORGAN STREET ELEVATED STATION PROJECT 07/11/2013 CHICAGO DEPARTMENT OF TRANSPORTATION ($221,136.42)
MORGAN STREET ELEVATED STATION PROJECT 06/22/2011 CHICAGO DEPARTMENT OF TRANSPORTATION $66,600.00
MORGAN STREET ELEVATED STATION PROJECT 06/27/2011 CHICAGO DEPARTMENT OF TRANSPORTATION ($9,299.49)