Original Contract

DUR in the Award Amount column means that the contract award total Depends Upon Requirements. A Depends Upon Requirements contract is an indefinite quantities contract in which the city places orders as needed. The vendor is not guaranteed any particular contract award amount.
Contract (PO) # Disclosure # Award Date Start Date End Date Original Award Amount
05/12/2009 Up To $2,000,000.00

Modifications/Amendments

Modification # Description Disclosure # Award Date Start Date End Date Amount
195761
JOC DEPT OF ENVIRONMENT FOR THE REMOVAL OF UNDERGROUND STORAGE TANKS (UST) AND THE REMEDIATION OF CONTAMINATED SITES 05/12/2009 05/13/2009 05/13/2011 DUR
JOC DEPT OF ENVIRONMENT FOR THE REMOVAL OF UNDERGROUND STORAGE TANKS (UST) AND THE REMEDIATION OF CONTAMINATED SITES 05/13/2009 05/13/2009 05/13/2010 DUR
JOC DEPT OF ENVIRONMENT FOR THE REMOVAL OF UNDERGROUND STORAGE TANKS (UST) AND THE REMEDIATION OF CONTAMINATED SITES 07/16/2010 05/13/2009 05/13/2011 $2,000,000.00
195764
JOC DEPT OF ENVIRONMENT FOR THE REMOVAL OF UNDERGROUND STORAGE TANKS (UST) AND THE REMEDIATION OF CONTAMINATED SITES 07/06/2011 05/13/2009 05/13/2011 $2,000,000.00
JOC DEPT OF ENVIRONMENT FOR THE REMOVAL OF UNDERGROUND STORAGE TANKS (UST) AND THE REMEDIATION OF CONTAMINATED SITES 07/07/2011 05/13/2009 05/12/2012 DUR
195766
JOC DEPT OF ENVIRONMENT FOR THE REMOVAL OF UNDERGROUND STORAGE TANKS (UST) AND THE REMEDIATION OF CONTAMINATED SITES 03/01/2012 05/13/2009 05/12/2013 $2,000,000.00
195767
JOC DEPT OF ENVIRONMENT FOR THE REMOVAL OF UNDERGROUND STORAGE TANKS (UST) AND THE REMEDIATION OF CONTAMINATED SITES 05/23/2013 05/13/2009 DUR
195768
JOC DEPT OF ENVIRONMENT FOR THE REMOVAL OF UNDERGROUND STORAGE TANKS (UST) AND THE REMEDIATION OF CONTAMINATED SITES 05/23/2013 05/13/2009 05/12/2013 DUR