City of Chicago

Procurement Services

We are the contracting authority for the procurement of goods and services for the City of Chicago

contract.detail.title

Contract Details

   View payment details

Original Contract

DUR in the Award Amount column means that the contract award total Depends Upon Requirements. A Depends Upon Requirements contract is an indefinite quantities contract in which the city places orders as needed. The vendor is not guaranteed any particular contract award amount.
Contract (PO) # Disclosure # Award Date Start Date End Date Department Original Award Amount
08/18/2006 OHARE MODERNIZATION PROJECT $32,715,000.00

Modifications/Amendments

Modification # Description Disclosure # Award Date Start Date End Date Department Amount
OMP NORTH AIRFIELD - NEW CONSTRUCTION NORTH AIRPORT TRAFFIC CONTROL TOWER 03/22/2007 OHARE MODERNIZATION PROJECT $5,500,000.00
1245811
OMP NORTH AIRFIELD - NEW CONSTRUCTION NORTH AIRPORT TRAFFIC CONTROL TOWER 01/04/2008 OHARE MODERNIZATION PROJECT $104,518.00
OMP NORTH AIRFIELD - NEW CONSTRUCTION NORTH AIRPORT TRAFFIC CONTROL TOWER 01/07/2008 OHARE MODERNIZATION PROJECT ($28,861.00)
OMP NORTH AIRFIELD - NEW CONSTRUCTION NORTH AIRPORT TRAFFIC CONTROL TOWER 01/25/2008 OHARE MODERNIZATION PROJECT $81,107.00
OMP NORTH AIRFIELD - NEW CONSTRUCTION NORTH AIRPORT TRAFFIC CONTROL TOWER 01/30/2008 OHARE MODERNIZATION PROJECT $20,922.00
OMP NORTH AIRFIELD - NEW CONSTRUCTION NORTH AIRPORT TRAFFIC CONTROL TOWER 03/24/2008 OHARE MODERNIZATION PROJECT $143,359.00
OMP NORTH AIRFIELD - NEW CONSTRUCTION NORTH AIRPORT TRAFFIC CONTROL TOWER 04/16/2008 OHARE MODERNIZATION PROJECT $7,471.00
OMP NORTH AIRFIELD - NEW CONSTRUCTION NORTH AIRPORT TRAFFIC CONTROL TOWER 05/19/2008 OHARE MODERNIZATION PROJECT $208,947.00
OMP NORTH AIRFIELD - NEW CONSTRUCTION NORTH AIRPORT TRAFFIC CONTROL TOWER 05/20/2008 OHARE MODERNIZATION PROJECT $58,357.00
OMP NORTH AIRFIELD - NEW CONSTRUCTION NORTH AIRPORT TRAFFIC CONTROL TOWER 03/29/2007 OHARE MODERNIZATION PROJECT $28,724.00
OMP NORTH AIRFIELD - NEW CONSTRUCTION NORTH AIRPORT TRAFFIC CONTROL TOWER 05/27/2008 OHARE MODERNIZATION PROJECT $285,156.00
OMP NORTH AIRFIELD - NEW CONSTRUCTION NORTH AIRPORT TRAFFIC CONTROL TOWER 06/16/2008 OHARE MODERNIZATION PROJECT $279,020.00
OMP NORTH AIRFIELD - NEW CONSTRUCTION NORTH AIRPORT TRAFFIC CONTROL TOWER 06/20/2008 OHARE MODERNIZATION PROJECT $225,000.00
OMP NORTH AIRFIELD - NEW CONSTRUCTION NORTH AIRPORT TRAFFIC CONTROL TOWER 06/29/2008 OHARE MODERNIZATION PROJECT $544,429.00
OMP NORTH AIRFIELD - NEW CONSTRUCTION NORTH AIRPORT TRAFFIC CONTROL TOWER 07/07/2008 OHARE MODERNIZATION PROJECT $203,223.00
OMP NORTH AIRFIELD - NEW CONSTRUCTION NORTH AIRPORT TRAFFIC CONTROL TOWER 07/14/2008 OHARE MODERNIZATION PROJECT $252,282.00
OMP NORTH AIRFIELD - NEW CONSTRUCTION NORTH AIRPORT TRAFFIC CONTROL TOWER 07/15/2008 OHARE MODERNIZATION PROJECT $79,543.00
OMP NORTH AIRFIELD - NEW CONSTRUCTION NORTH AIRPORT TRAFFIC CONTROL TOWER 08/25/2008 OHARE MODERNIZATION PROJECT $27,000.00
OMP NORTH AIRFIELD - NEW CONSTRUCTION NORTH AIRPORT TRAFFIC CONTROL TOWER 09/23/2008 OHARE MODERNIZATION PROJECT $67,359.00
OMP NORTH AIRFIELD - NEW CONSTRUCTION NORTH AIRPORT TRAFFIC CONTROL TOWER 12/03/2008 OHARE MODERNIZATION PROJECT $191,217.00
OMP NORTH AIRFIELD - NEW CONSTRUCTION NORTH AIRPORT TRAFFIC CONTROL TOWER 04/10/2007 OHARE MODERNIZATION PROJECT $21,515.00
OMP NORTH AIRFIELD - NEW CONSTRUCTION NORTH AIRPORT TRAFFIC CONTROL TOWER 12/05/2008 OHARE MODERNIZATION PROJECT $103,348.00
OMP NORTH AIRFIELD - NEW CONSTRUCTION NORTH AIRPORT TRAFFIC CONTROL TOWER 12/11/2008 OHARE MODERNIZATION PROJECT $13,348.00
OMP NORTH AIRFIELD - NEW CONSTRUCTION NORTH AIRPORT TRAFFIC CONTROL TOWER 12/18/2008 OHARE MODERNIZATION PROJECT $52,131.00
OMP NORTH AIRFIELD - NEW CONSTRUCTION NORTH AIRPORT TRAFFIC CONTROL TOWER 02/05/2009 OHARE MODERNIZATION PROJECT $100,343.00
OMP NORTH AIRFIELD - NEW CONSTRUCTION NORTH AIRPORT TRAFFIC CONTROL TOWER 02/06/2009 OHARE MODERNIZATION PROJECT $28,920.00
OMP NORTH AIRFIELD - NEW CONSTRUCTION NORTH AIRPORT TRAFFIC CONTROL TOWER 03/23/2009 OHARE MODERNIZATION PROJECT $402,124.00
OMP NORTH AIRFIELD - NEW CONSTRUCTION NORTH AIRPORT TRAFFIC CONTROL TOWER 03/27/2009 OHARE MODERNIZATION PROJECT ($50,000.00)
OMP NORTH AIRFIELD - NEW CONSTRUCTION NORTH AIRPORT TRAFFIC CONTROL TOWER 04/03/2009 OHARE MODERNIZATION PROJECT $558,952.00
1245838
OMP NORTH AIRFIELD - NEW CONSTRUCTION NORTH AIRPORT TRAFFIC CONTROL TOWER 04/06/2009 OHARE MODERNIZATION PROJECT $120,000.00
OMP NORTH AIRFIELD - NEW CONSTRUCTION NORTH AIRPORT TRAFFIC CONTROL TOWER 04/08/2009 OHARE MODERNIZATION PROJECT $39,322.00
OMP NORTH AIRFIELD - NEW CONSTRUCTION NORTH AIRPORT TRAFFIC CONTROL TOWER 08/15/2007 OHARE MODERNIZATION PROJECT $25,682.00
OMP NORTH AIRFIELD - NEW CONSTRUCTION NORTH AIRPORT TRAFFIC CONTROL TOWER 04/09/2009 OHARE MODERNIZATION PROJECT ($4,473.00)
OMP NORTH AIRFIELD - NEW CONSTRUCTION NORTH AIRPORT TRAFFIC CONTROL TOWER 05/14/2009 OHARE MODERNIZATION PROJECT $6,650.00
OMP NORTH AIRFIELD - NEW CONSTRUCTION NORTH AIRPORT TRAFFIC CONTROL TOWER 05/22/2009 OHARE MODERNIZATION PROJECT ($13,581.00)
OMP NORTH AIRFIELD - NEW CONSTRUCTION NORTH AIRPORT TRAFFIC CONTROL TOWER 07/09/2009 OHARE MODERNIZATION PROJECT $19,500.00
OMP NORTH AIRFIELD - NEW CONSTRUCTION NORTH AIRPORT TRAFFIC CONTROL TOWER 11/25/2009 OHARE MODERNIZATION PROJECT ($20,823.00)
OMP NORTH AIRFIELD - NEW CONSTRUCTION NORTH AIRPORT TRAFFIC CONTROL TOWER 12/03/2007 OHARE MODERNIZATION PROJECT $18,104.00
OMP NORTH AIRFIELD - NEW CONSTRUCTION NORTH AIRPORT TRAFFIC CONTROL TOWER 12/07/2007 OHARE MODERNIZATION PROJECT $118,009.00
OMP NORTH AIRFIELD - NEW CONSTRUCTION NORTH AIRPORT TRAFFIC CONTROL TOWER 12/18/2007 OHARE MODERNIZATION PROJECT $44,319.00
OMP NORTH AIRFIELD - NEW CONSTRUCTION NORTH AIRPORT TRAFFIC CONTROL TOWER 12/20/2007 OHARE MODERNIZATION PROJECT $314,176.00
OMP NORTH AIRFIELD - NEW CONSTRUCTION NORTH AIRPORT TRAFFIC CONTROL TOWER 12/27/2007 OHARE MODERNIZATION PROJECT $25,154.00