Contract (PO) # | Disclosure # | Award Date | Start Date | End Date | Department | Original Award Amount |
---|---|---|---|---|---|---|
02/14/2020 | 02/18/2020 | 02/18/2022 | DEPARTMENT OF WATER MANAGEMENT | Up To $10,163,443.00 |
Modification # | Description | Disclosure # | Award Date | Start Date | End Date | Department | Amount |
---|---|---|---|---|---|---|---|
1014258: Ancillary Sewer Construction - Central Area / DWM Project Number 7495B | 05/09/2023 | 02/18/2020 | 11/30/2023 | DEPARTMENT OF WATER MANAGEMENT | DUR | ||
1191113
| 1014258: Ancillary Sewer Construction - Central Area / DWM Project Number 7495B | 09/09/2022 | 02/18/2020 | 02/28/2023 | DEPARTMENT OF WATER MANAGEMENT | $5,335,800.00 | |
1014258: Ancillary Sewer Construction - Central Area / DWM Project Number 7495B PO#119111/CM#02/PCM#03/Price adjustment 1.01397/$0.00/No Days | 04/28/2021 | 02/18/2020 | 02/18/2022 | DEPARTMENT OF WATER MANAGEMENT | DUR | ||
1014258: Ancillary Sewer Construction - Central Area / DWM Project Number 7495B | 12/29/2020 | 02/18/2020 | 02/18/2022 | DEPARTMENT OF WATER MANAGEMENT | DUR |