Contract (PO) # | Disclosure # | Award Date | Start Date | End Date | Department | Original Award Amount |
---|---|---|---|---|---|---|
P011730
| 06/06/2000 | 06/06/2000 | 11/01/2000 | CHICAGO DEPARTMENT OF TRANSPORTATION | $5,278,781.12 |
Modification # | Description | Disclosure # | Award Date | Start Date | End Date | Department | Amount |
---|---|---|---|---|---|---|---|
P0117301
| PN84P011730 TO ADVERTISE | 05/14/2008 | CHICAGO DEPARTMENT OF TRANSPORTATION | ($2,326.38) | |||
P011730P21561
| LOOP LIGHTING IMPROVEMENT - DEARBORN STREET - PHASE 2 - FROM CONGRESS TO WACKER | 11/14/2002 | 06/07/2000 | 01/31/2002 | CHICAGO DEPARTMENT OF TRANSPORTATION | $58,000.00 | |
P011730P21042
| LOOP LIGHTING IMPROVEMENT - DEARBORN STREET - PHASE 2 - FROM CONGRESS TO WACKER | 06/05/2002 | 06/07/2000 | 01/31/2002 | CHICAGO DEPARTMENT OF TRANSPORTATION | $5,273.46 | |
P011730P20731
| LOOP LIGHTING IMPROVEMENT - DEARBORN STREET - PHASE 2 - FROM CONGRESS TO WACKER | 03/15/2002 | 06/07/2000 | 01/31/2002 | CHICAGO DEPARTMENT OF TRANSPORTATION | $0.00 | |
P011730P11771
| LOOP LIGHTING IMPROVEMENT - DEARBORN STREET - PHASE 2 - FROM CONGRESS TO WACKER | 01/14/2002 | 06/07/2000 | 07/30/2001 | CHICAGO DEPARTMENT OF TRANSPORTATION | $145,000.00 | |
P011730P11482
| LOOP LIGHTING IMPROVEMENT - DEARBORN STREET - PHASE 2 - FROM CONGRESS TO WACKER | 10/10/2001 | 06/07/2000 | 11/01/2000 | CHICAGO DEPARTMENT OF TRANSPORTATION | $0.00 | |
P011730P11212
| LOOP LIGHTING IMPROVEMENT - DEARBORN STREET - PHASE 2 - FROM CONGRESS TO WACKER | 08/10/2001 | 06/07/2000 | 11/01/2000 | CHICAGO DEPARTMENT OF TRANSPORTATION | $25,000.00 | |
P011730P10701
| LOOP LIGHTING IMPROVEMENT - DEARBORN STREET - PHASE 2 - FROM CONGRESS TO WACKER | 04/09/2001 | CHICAGO DEPARTMENT OF TRANSPORTATION | ($20,210.00) | |||
P011730P10617
| LOOP LIGHTING IMPROVEMENT - DEARBORN STREET - PHASE 2 - FROM CONGRESS TO WACKER | 02/15/2001 | CHICAGO DEPARTMENT OF TRANSPORTATION | $55,970.00 | |||
P011730P01201
| LOOP LIGHTING IMPROVEMENT - DEARBORN STREET - PHASE 2 - FROM CONGRESS TO WACKER | 01/10/2001 | CHICAGO DEPARTMENT OF TRANSPORTATION | $40,000.00 | |||
P011730P01147
| LOOP LIGHTING IMPROVEMENT - DEARBORN STREET - PHASE 2 - FROM CONGRESS TO WACKER | 12/07/2000 | 06/07/2000 | 11/01/2000 | CHICAGO DEPARTMENT OF TRANSPORTATION | $29,200.00 | |
P011730P01030
| LOOP LIGHTING IMPROVEMENT - DEARBORN STREET - PHASE 2 - FROM CONGRESS TO WACKER | 10/25/2000 | CHICAGO DEPARTMENT OF TRANSPORTATION | $10,000.00 | |||
P011730P00874
| LOOP LIGHTING IMPROVEMENT - DEARBORN STREET - PHASE 2 - FROM CONGRESS TO WACKER | 08/17/2000 | 06/07/2000 | 11/01/2000 | CHICAGO DEPARTMENT OF TRANSPORTATION | $5,500.00 |