Contract (PO) # | Disclosure # | Award Date | Start Date | End Date | Department | Original Award Amount |
---|---|---|---|---|---|---|
02/15/2019 | OHARE MODERNIZATION PROJECT | $94,983,087.24 |
Modification # | Description | Disclosure # | Award Date | Start Date | End Date | Department | Amount |
---|---|---|---|---|---|---|---|
9412612
| OMP Runway 9C-27C Bid Pkg #3 & RWY 4L-22R Rehab (Spec 862852) | 10/17/2019 | OHARE MODERNIZATION PROJECT | $14,712.06 | |||
9412613
| OMP Runway 9C-27C Bid Pkg #3 & RWY 4L-22R Rehab (Spec 862852) | 11/13/2019 | OHARE MODERNIZATION PROJECT | $72,669.49 | |||
9412614
| OMP Runway 9C-27C Bid Pkg #3 & RWY 4L-22R Rehab (Spec 862852) | 11/13/2019 | OHARE MODERNIZATION PROJECT | $443,195.64 | |||
OMP Runway 9C-27C Bid Pkg #3 & RWY 4L-22R Rehab (Spec 862852) | 11/13/2019 | OHARE MODERNIZATION PROJECT | $135,000.00 | ||||
OMP Runway 9C-27C Bid Pkg #3 & RWY 4L-22R Rehab (Spec 862852) | 11/26/2019 | OHARE MODERNIZATION PROJECT | $190,000.00 | ||||
9412617
| OMP Runway 9C-27C Bid Pkg #3 & RWY 4L-22R Rehab (Spec 862852) | 12/04/2019 | OHARE MODERNIZATION PROJECT | $4,425.40 | |||
9412618
| OMP Runway 9C-27C Bid Pkg #3 & RWY 4L-22R Rehab (Spec 862852) | 12/04/2019 | OHARE MODERNIZATION PROJECT | $13,932.42 | |||
9412619
| OMP Runway 9C-27C Bid Pkg #3 & RWY 4L-22R Rehab (Spec 862852) | 12/06/2019 | OHARE MODERNIZATION PROJECT | $14,210.00 | |||
941262
| OMP Runway 9C-27C Bid Pkg #3 & RWY 4L-22R Rehab (Spec 862852) | 06/10/2019 | OHARE MODERNIZATION PROJECT | $25,924.15 | |||
9412620
| OMP Runway 9C-27C Bid Pkg #3 & RWY 4L-22R Rehab (Spec 862852) | 12/09/2019 | OHARE MODERNIZATION PROJECT | $20,431.95 | |||
9412621
| OMP Runway 9C-27C Bid Pkg #3 & RWY 4L-22R Rehab (Spec 862852) | 12/11/2019 | OHARE MODERNIZATION PROJECT | $3,589.41 | |||
9412622
| OMP Runway 9C-27C Bid Pkg #3 & RWY 4L-22R Rehab (Spec 862852) | 12/18/2019 | OHARE MODERNIZATION PROJECT | $61,832.42 | |||
9412623
| OMP Runway 9C-27C Bid Pkg #3 & RWY 4L-22R Rehab (Spec 862852) | 01/22/2020 | OHARE MODERNIZATION PROJECT | $10,410.67 | |||
9412624
| OMP Runway 9C-27C Bid Pkg #3 & RWY 4L-22R Rehab (Spec 862852) | 02/24/2020 | OHARE MODERNIZATION PROJECT | $105,445.88 | |||
9412625
| OMP Runway 9C-27C Bid Pkg #3 & RWY 4L-22R Rehab (Spec 862852) | 02/27/2020 | OHARE MODERNIZATION PROJECT | $145,230.58 | |||
9412626
| OMP Runway 9C-27C Bid Pkg #3 & RWY 4L-22R Rehab (Spec 862852) | 03/18/2020 | OHARE MODERNIZATION PROJECT | $11,298.98 | |||
9412627
| OMP Runway 9C-27C Bid Pkg #3 & RWY 4L-22R Rehab (Spec 862852) | 05/29/2020 | OHARE MODERNIZATION PROJECT | $40,425.51 | |||
9412628
| OMP Runway 9C-27C Bid Pkg #3 & RWY 4L-22R Rehab (Spec 862852) | 06/03/2020 | OHARE MODERNIZATION PROJECT | $11,656.93 | |||
9412629
| OMP Runway 9C-27C Bid Pkg #3 & RWY 4L-22R Rehab (Spec 862852) | 06/10/2020 | OHARE MODERNIZATION PROJECT | $32,429.10 | |||
941263
| OMP Runway 9C-27C Bid Pkg #3 & RWY 4L-22R Rehab (Spec 862852) | 06/26/2019 | OHARE MODERNIZATION PROJECT | ($255,937.35) | |||
9412630
| OMP Runway 9C-27C Bid Pkg #3 & RWY 4L-22R Rehab (Spec 862852) | 06/17/2020 | OHARE MODERNIZATION PROJECT | $484,000.00 | |||
9412631
| OMP Runway 9C-27C Bid Pkg #3 & RWY 4L-22R Rehab (Spec 862852) | 06/17/2020 | OHARE MODERNIZATION PROJECT | $188,000.00 | |||
9412633
| OMP Runway 9C-27C Bid Pkg #3 & RWY 4L-22R Rehab (Spec 862852) | 07/06/2020 | OHARE MODERNIZATION PROJECT | ($119,706.39) | |||
9412634
| OMP Runway 9C-27C Bid Pkg #3 & RWY 4L-22R Rehab (Spec 862852) | 07/09/2020 | OHARE MODERNIZATION PROJECT | $870,315.15 | |||
9412635
| OMP Runway 9C-27C Bid Pkg #3 & RWY 4L-22R Rehab (Spec 862852) | 07/16/2020 | OHARE MODERNIZATION PROJECT | $400,368.00 | |||
9412636
| OMP Runway 9C-27C Bid Pkg #3 & RWY 4L-22R Rehab (Spec 862852) | 07/27/2020 | OHARE MODERNIZATION PROJECT | ($31,308.28) | |||
9412637
| OMP Runway 9C-27C Bid Pkg #3 & RWY 4L-22R Rehab (Spec 862852) | 07/28/2020 | OHARE MODERNIZATION PROJECT | $41,220.38 | |||
9412638
| OMP Runway 9C-27C Bid Pkg #3 & RWY 4L-22R Rehab (Spec 862852) | 07/28/2020 | OHARE MODERNIZATION PROJECT | $15,350.00 | |||
9412639
| OMP Runway 9C-27C Bid Pkg #3 & RWY 4L-22R Rehab (Spec 862852) | 07/28/2020 | OHARE MODERNIZATION PROJECT | $33,000.00 | |||
941264
| OMP Runway 9C-27C Bid Pkg #3 & RWY 4L-22R Rehab (Spec 862852) | 07/02/2019 | OHARE MODERNIZATION PROJECT | $15,215.47 | |||
9412640
| OMP Runway 9C-27C Bid Pkg #3 & RWY 4L-22R Rehab (Spec 862852) | 07/29/2020 | OHARE MODERNIZATION PROJECT | $27,000.00 | |||
9412643
| OMP Runway 9C-27C Bid Pkg #3 & RWY 4L-22R Rehab (Spec 862852) | 08/24/2020 | OHARE MODERNIZATION PROJECT | $155,980.51 | |||
9412644
| OMP Runway 9C-27C Bid Pkg #3 & RWY 4L-22R Rehab (Spec 862852) | 08/25/2020 | OHARE MODERNIZATION PROJECT | ($106,342.64) | |||
9412645
| OMP Runway 9C-27C Bid Pkg #3 & RWY 4L-22R Rehab (Spec 862852) | 09/01/2020 | OHARE MODERNIZATION PROJECT | ($68,066.50) | |||
9412646
| OMP Runway 9C-27C Bid Pkg #3 & RWY 4L-22R Rehab (Spec 862852) | 09/30/2020 | OHARE MODERNIZATION PROJECT | $269,759.38 | |||
9412647
| OMP Runway 9C-27C Bid Pkg #3 & RWY 4L-22R Rehab (Spec 862852) | 10/08/2020 | OHARE MODERNIZATION PROJECT | $51,740.70 | |||
9412648
| OMP Runway 9C-27C Bid Pkg #3 & RWY 4L-22R Rehab (Spec 862852) | 10/27/2020 | OHARE MODERNIZATION PROJECT | $141,865.64 | |||
9412649
| OMP Runway 9C-27C Bid Pkg #3 & RWY 4L-22R Rehab (Spec 862852) | 11/17/2020 | OHARE MODERNIZATION PROJECT | $90,673.34 | |||
941265
| OMP Runway 9C-27C Bid Pkg #3 & RWY 4L-22R Rehab (Spec 862852) | 09/13/2019 | OHARE MODERNIZATION PROJECT | $1,070.74 | |||
9412650
| OMP Runway 9C-27C Bid Pkg #3 & RWY 4L-22R Rehab (Spec 862852) | 11/18/2020 | OHARE MODERNIZATION PROJECT | $860.32 | |||
9412651
| OMP Runway 9C-27C Bid Pkg #3 & RWY 4L-22R Rehab (Spec 862852) | 12/29/2020 | OHARE MODERNIZATION PROJECT | $78,632.35 | |||
9412652
| OMP Runway 9C-27C Bid Pkg #3 & RWY 4L-22R Rehab (Spec 862852) | 01/07/2021 | OHARE MODERNIZATION PROJECT | $29,974.18 | |||
9412653
| OMP Runway 9C-27C Bid Pkg #3 & RWY 4L-22R Rehab (Spec 862852) | 01/07/2021 | OHARE MODERNIZATION PROJECT | ($10,268.36) | |||
9412654
| OMP Runway 9C-27C Bid Pkg #3 & RWY 4L-22R Rehab (Spec 862852) | 01/15/2021 | OHARE MODERNIZATION PROJECT | $137,861.19 | |||
9412655
| OMP Runway 9C-27C Bid Pkg #3 & RWY 4L-22R Rehab (Spec 862852) | 01/19/2021 | OHARE MODERNIZATION PROJECT | ($21,445.80) | |||
9412657
| OMP Runway 9C-27C Bid Pkg #3 & RWY 4L-22R Rehab (Spec 862852) | 02/25/2021 | OHARE MODERNIZATION PROJECT | $279.53 | |||
9412658
| OMP Runway 9C-27C Bid Pkg #3 & RWY 4L-22R Rehab (Spec 862852) | 03/02/2021 | OHARE MODERNIZATION PROJECT | ($119,997.90) | |||
9412659
| OMP Runway 9C-27C Bid Pkg #3 & RWY 4L-22R Rehab (Spec 862852) | 03/09/2021 | OHARE MODERNIZATION PROJECT | $21,749.70 | |||
941266
| OMP Runway 9C-27C Bid Pkg #3 & RWY 4L-22R Rehab (Spec 862852) | 09/23/2019 | OHARE MODERNIZATION PROJECT | $30,578.40 | |||
9412660
| OMP Runway 9C-27C Bid Pkg #3 & RWY 4L-22R Rehab (Spec 862852) | 03/10/2021 | OHARE MODERNIZATION PROJECT | ($22,759.63) | |||
9412661
| OMP Runway 9C-27C Bid Pkg #3 & RWY 4L-22R Rehab (Spec 862852) | 03/16/2021 | OHARE MODERNIZATION PROJECT | ($100,000.00) | |||
9412662
| OMP Runway 9C-27C Bid Pkg #3 & RWY 4L-22R Rehab (Spec 862852) | 03/30/2021 | OHARE MODERNIZATION PROJECT | $41,312.82 | |||
9412663
| OMP Runway 9C-27C Bid Pkg #3 & RWY 4L-22R Rehab (Spec 862852) | 04/06/2021 | OHARE MODERNIZATION PROJECT | $869,992.88 | |||
9412664
| OMP Runway 9C-27C Bid Pkg #3 & RWY 4L-22R Rehab (Spec 862852) | 04/13/2021 | OHARE MODERNIZATION PROJECT | ($752,772.07) | |||
9412665
| OMP Runway 9C-27C Bid Pkg #3 & RWY 4L-22R Rehab (Spec 862852) | 07/16/2021 | OHARE MODERNIZATION PROJECT | $534,000.00 | |||
9412666
| OMP Runway 9C-27C Bid Pkg #3 & RWY 4L-22R Rehab (Spec 862852) | 08/09/2021 | OHARE MODERNIZATION PROJECT | ($398,371.50) | |||
9412667
| OMP Runway 9C-27C Bid Pkg #3 & RWY 4L-22R Rehab (Spec 862852) | 09/02/2021 | OHARE MODERNIZATION PROJECT | $398,371.50 | |||
9412668
| OMP Runway 9C-27C Bid Pkg #3 & RWY 4L-22R Rehab (Spec 862852) | 01/26/2022 | OHARE MODERNIZATION PROJECT | $69,988.10 | |||
9412669
| OMP Runway 9C-27C Bid Pkg #3 & RWY 4L-22R Rehab (Spec 862852) | 02/01/2022 | OHARE MODERNIZATION PROJECT | $352,111.55 | |||
941267
| OMP Runway 9C-27C Bid Pkg #3 & RWY 4L-22R Rehab (Spec 862852) | 09/25/2019 | OHARE MODERNIZATION PROJECT | $40.00 | |||
9412670
| OMP Runway 9C-27C Bid Pkg #3 & RWY 4L-22R Rehab (Spec 862852) | 02/04/2022 | OHARE MODERNIZATION PROJECT | ($883,112.57) | |||
9412671
| OMP Runway 9C-27C Bid Pkg #3 & RWY 4L-22R Rehab (Spec 862852) | 02/09/2022 | OHARE MODERNIZATION PROJECT | $319,125.80 | |||
9412672
| OMP Runway 9C-27C Bid Pkg #3 & RWY 4L-22R Rehab (Spec 862852) | 03/18/2022 | OHARE MODERNIZATION PROJECT | $45,842.00 | |||
941268
| OMP Runway 9C-27C Bid Pkg #3 & RWY 4L-22R Rehab (Spec 862852) | 09/27/2019 | OHARE MODERNIZATION PROJECT | $7,878.43 |