Original Contract

DUR in the Award Amount column means that the contract award total Depends Upon Requirements. A Depends Upon Requirements contract is an indefinite quantities contract in which the city places orders as needed. The vendor is not guaranteed any particular contract award amount.
Contract (PO) # Disclosure # Award Date Start Date End Date Department Original Award Amount
06/28/2016 OHARE MODERNIZATION PROJECT $69,849,082.12

Modifications/Amendments

Modification # Description Disclosure # Award Date Start Date End Date Department Amount
415671
OMP Runway 9C-27C East Package - ORD, Spec 163099 08/31/2016 OHARE MODERNIZATION PROJECT $35,000.00
4156710
OMP Runway 9C-27C East Package - ORD, Spec 163099 11/09/2016 OHARE MODERNIZATION PROJECT $22,375.00
41567101
OMP Runway 9C-27C East Package - ORD, Spec 163099 12/18/2019 OHARE MODERNIZATION PROJECT $20.00
4156711
OMP Runway 9C-27C East Package - ORD, Spec 163099 11/10/2016 OHARE MODERNIZATION PROJECT $240,349.71
4156712
OMP Runway 9C-27C East Package - ORD, Spec 163099 11/21/2016 OHARE MODERNIZATION PROJECT $103,392.32
OMP Runway 9C-27C East Package - ORD, Spec 163099 12/29/2016 OHARE MODERNIZATION PROJECT $403,485.00
4156714
OMP Runway 9C-27C East Package - ORD, Spec 163099 12/30/2016 OHARE MODERNIZATION PROJECT $236,400.00
4156715
OMP Runway 9C-27C East Package - ORD, Spec 163099 01/10/2017 OHARE MODERNIZATION PROJECT ($93,800.00)
4156716
OMP Runway 9C-27C East Package - ORD, Spec 163099 01/13/2017 OHARE MODERNIZATION PROJECT ($272,537.88)
4156717
OMP Runway 9C-27C East Package - ORD, Spec 163099 01/17/2017 OHARE MODERNIZATION PROJECT $3,384.15
4156718
OMP Runway 9C-27C East Package - ORD, Spec 163099 01/18/2017 OHARE MODERNIZATION PROJECT $267,001.42
OMP Runway 9C-27C East Package - ORD, Spec 163099 01/19/2017 OHARE MODERNIZATION PROJECT $5,000.00
415672
OMP Runway 9C-27C East Package - ORD, Spec 163099 09/02/2016 OHARE MODERNIZATION PROJECT ($1,313,047.55)
4156720
OMP Runway 9C-27C East Package - ORD, Spec 163099 01/27/2017 OHARE MODERNIZATION PROJECT ($1,228,691.93)
OMP Runway 9C-27C East Package - ORD, Spec 163099 02/15/2017 OHARE MODERNIZATION PROJECT $240,314.36
OMP Runway 9C-27C East Package - ORD, Spec 163099 02/17/2017 OHARE MODERNIZATION PROJECT $40,000.00
4156725
OMP Runway 9C-27C East Package - ORD, Spec 163099 03/16/2017 OHARE MODERNIZATION PROJECT ($151,085.80)
4156726
OMP Runway 9C-27C East Package - ORD, Spec 163099 04/11/2017 OHARE MODERNIZATION PROJECT $161,383.60
4156727
OMP Runway 9C-27C East Package - ORD, Spec 163099 05/09/2017 OHARE MODERNIZATION PROJECT $235,020.15
4156728
OMP Runway 9C-27C East Package - ORD, Spec 163099 05/09/2017 OHARE MODERNIZATION PROJECT $53,886.16
4156729
OMP Runway 9C-27C East Package - ORD, Spec 163099 05/11/2017 OHARE MODERNIZATION PROJECT $200,970.73
415673
OMP Runway 9C-27C East Package - ORD, Spec 163099 09/07/2016 OHARE MODERNIZATION PROJECT ($37,307.16)
4156730
OMP Runway 9C-27C East Package - ORD, Spec 163099 05/31/2017 OHARE MODERNIZATION PROJECT $455,000.00
4156732
OMP Runway 9C-27C East Package - ORD, Spec 163099 06/01/2017 OHARE MODERNIZATION PROJECT $104,332.91
4156733
OMP Runway 9C-27C East Package - ORD, Spec 163099 06/08/2017 OHARE MODERNIZATION PROJECT $208,100.86
4156734
OMP Runway 9C-27C East Package - ORD, Spec 163099 07/05/2017 OHARE MODERNIZATION PROJECT $28,507.30
OMP Runway 9C-27C East Package - ORD, Spec 163099 07/05/2017 OHARE MODERNIZATION PROJECT $35,000.00
OMP Runway 9C-27C East Package - ORD, Spec 163099 07/07/2017 OHARE MODERNIZATION PROJECT $168,525.43
4156737
OMP Runway 9C-27C East Package - ORD, Spec 163099 09/07/2017 OHARE MODERNIZATION PROJECT $174,308.00
4156738
OMP Runway 9C-27C East Package - ORD, Spec 163099 09/07/2017 OHARE MODERNIZATION PROJECT $148,592.07
OMP Runway 9C-27C East Package - ORD, Spec 163099 09/22/2017 OHARE MODERNIZATION PROJECT $39,989.07
415674
OMP Runway 9C-27C East Package - ORD, Spec 163099 10/18/2016 OHARE MODERNIZATION PROJECT $98,155.33
OMP Runway 9C-27C East Package - ORD, Spec 163099 09/25/2017 OHARE MODERNIZATION PROJECT $67,406.85
OMP Runway 9C-27C East Package - ORD, Spec 163099 09/29/2017 OHARE MODERNIZATION PROJECT $34,771.72
4156742
OMP Runway 9C-27C East Package - ORD, Spec 163099 10/20/2017 OHARE MODERNIZATION PROJECT $797,430.00
4156743
OMP Runway 9C-27C East Package - ORD, Spec 163099 11/20/2017 OHARE MODERNIZATION PROJECT $30,667.55
OMP Runway 9C-27C East Package - ORD, Spec 163099 11/28/2017 OHARE MODERNIZATION PROJECT $1,042,632.20
OMP Runway 9C-27C East Package - ORD, Spec 163099 11/29/2017 OHARE MODERNIZATION PROJECT $140,631.13
4156746
OMP Runway 9C-27C East Package - ORD, Spec 163099 12/04/2017 OHARE MODERNIZATION PROJECT ($521,986.60)
OMP Runway 9C-27C East Package - ORD, Spec 163099 12/06/2017 OHARE MODERNIZATION PROJECT $59,235.80
4156748
OMP Runway 9C-27C East Package - ORD, Spec 163099 12/08/2017 OHARE MODERNIZATION PROJECT ($1,510,435.02)
OMP Runway 9C-27C East Package - ORD, Spec 163099 12/11/2017 OHARE MODERNIZATION PROJECT $1,297,897.21
415675
OMP Runway 9C-27C East Package - ORD, Spec 163099 10/28/2016 OHARE MODERNIZATION PROJECT $180,391.00
4156750
OMP Runway 9C-27C East Package - ORD, Spec 163099 12/13/2017 OHARE MODERNIZATION PROJECT $167,843.35
4156751
OMP Runway 9C-27C East Package - ORD, Spec 163099 01/03/2018 OHARE MODERNIZATION PROJECT $23,642.64
4156752
OMP Runway 9C-27C East Package - ORD, Spec 163099 01/05/2018 OHARE MODERNIZATION PROJECT $75,162.00
4156753
OMP Runway 9C-27C East Package - ORD, Spec 163099 01/16/2018 OHARE MODERNIZATION PROJECT $19,642.11
4156754
OMP Runway 9C-27C East Package - ORD, Spec 163099 01/17/2018 OHARE MODERNIZATION PROJECT $30,825.02
4156755
OMP Runway 9C-27C East Package - ORD, Spec 163099 02/22/2018 OHARE MODERNIZATION PROJECT $42,330.44
4156756
OMP Runway 9C-27C East Package - ORD, Spec 163099 02/26/2018 OHARE MODERNIZATION PROJECT $3,928.77
OMP Runway 9C-27C East Package - ORD, Spec 163099 03/01/2018 OHARE MODERNIZATION PROJECT $43,302.98
OMP Runway 9C-27C East Package - ORD, Spec 163099 03/01/2018 OHARE MODERNIZATION PROJECT $4,857.60
4156759
OMP Runway 9C-27C East Package - ORD, Spec 163099 03/16/2018 OHARE MODERNIZATION PROJECT ($129,746.14)
415676
OMP Runway 9C-27C East Package - ORD, Spec 163099 10/31/2016 OHARE MODERNIZATION PROJECT ($156,927.40)
4156760
OMP Runway 9C-27C East Package - ORD, Spec 163099 03/20/2018 OHARE MODERNIZATION PROJECT ($850,000.00)
OMP Runway 9C-27C East Package - ORD, Spec 163099 03/26/2018 OHARE MODERNIZATION PROJECT $100,000.00
OMP Runway 9C-27C East Package - ORD, Spec 163099 04/03/2018 OHARE MODERNIZATION PROJECT $9,581.74
OMP Runway 9C-27C East Package - ORD, Spec 163099 04/04/2018 OHARE MODERNIZATION PROJECT $259,001.57
OMP Runway 9C-27C East Package - ORD, Spec 163099 04/05/2018 OHARE MODERNIZATION PROJECT $15,336.03
OMP Runway 9C-27C East Package - ORD, Spec 163099 04/13/2018 OHARE MODERNIZATION PROJECT $137,377.69
OMP Runway 9C-27C East Package - ORD, Spec 163099 04/13/2018 OHARE MODERNIZATION PROJECT $18,487.35
4156768
OMP Runway 9C-27C East Package - ORD, Spec 163099 04/16/2018 OHARE MODERNIZATION PROJECT ($38,743.26)
4156769
OMP Runway 9C-27C East Package - ORD, Spec 163099 06/04/2018 OHARE MODERNIZATION PROJECT $24,600.00
415677
OMP Runway 9C-27C East Package - ORD, Spec 163099 11/04/2016 OHARE MODERNIZATION PROJECT $83,796.77
OMP Runway 9C-27C East Package - ORD, Spec 163099 06/05/2018 OHARE MODERNIZATION PROJECT $17,931.73
4156771
OMP Runway 9C-27C East Package - ORD, Spec 163099 06/06/2018 OHARE MODERNIZATION PROJECT $21,431.26
OMP Runway 9C-27C East Package - ORD, Spec 163099 06/08/2018 OHARE MODERNIZATION PROJECT $11,665.99
4156773
OMP Runway 9C-27C East Package - ORD, Spec 163099 06/11/2018 OHARE MODERNIZATION PROJECT $16,383.38
OMP Runway 9C-27C East Package - ORD, Spec 163099 06/22/2018 OHARE MODERNIZATION PROJECT $70,487.44
4156775
OMP Runway 9C-27C East Package - ORD, Spec 163099 06/28/2018 OHARE MODERNIZATION PROJECT $13,400.00
4156776
OMP Runway 9C-27C East Package - ORD, Spec 163099 06/29/2018 OHARE MODERNIZATION PROJECT $109,800.00
4156777
OMP Runway 9C-27C East Package - ORD, Spec 163099 07/25/2018 OHARE MODERNIZATION PROJECT $240,184.66
OMP Runway 9C-27C East Package - ORD, Spec 163099 07/26/2018 OHARE MODERNIZATION PROJECT $9,980.46
OMP Runway 9C-27C East Package - ORD, Spec 163099 08/21/2018 OHARE MODERNIZATION PROJECT $89,922.73
OMP Runway 9C-27C East Package - ORD, Spec 163099 11/08/2016 OHARE MODERNIZATION PROJECT $1,313,047.55
4156780
OMP Runway 9C-27C East Package - ORD, Spec 163099 10/02/2018 OHARE MODERNIZATION PROJECT $98,079.54
4156782
OMP Runway 9C-27C East Package - ORD, Spec 163099 11/01/2018 OHARE MODERNIZATION PROJECT ($56,146.87)
4156783
OMP Runway 9C-27C East Package - ORD, Spec 163099 11/02/2018 OHARE MODERNIZATION PROJECT ($105,207.78)
4156784
OMP Runway 9C-27C East Package - ORD, Spec 163099 11/15/2018 OHARE MODERNIZATION PROJECT $13,537.49
4156785
OMP Runway 9C-27C East Package - ORD, Spec 163099 11/16/2018 OHARE MODERNIZATION PROJECT $21,839.11
4156786
OMP Runway 9C-27C East Package - ORD, Spec 163099 03/08/2019 OHARE MODERNIZATION PROJECT ($11,758.67)
OMP Runway 9C-27C East Package - ORD, Spec 163099 04/19/2019 OHARE MODERNIZATION PROJECT $31,712.19
OMP Runway 9C-27C East Package - ORD, Spec 163099 04/24/2019 OHARE MODERNIZATION PROJECT $80,190.20
415679
OMP Runway 9C-27C East Package - ORD, Spec 163099 11/09/2016 OHARE MODERNIZATION PROJECT ($702,475.22)
4156790
OMP Runway 9C-27C East Package - ORD, Spec 163099 04/26/2019 OHARE MODERNIZATION PROJECT ($1,140,763.47)
OMP Runway 9C-27C East Package - ORD, Spec 163099 05/16/2019 OHARE MODERNIZATION PROJECT ($1,149,573.10)
OMP Runway 9C-27C East Package - ORD, Spec 163099 05/17/2019 OHARE MODERNIZATION PROJECT $230,742.30
OMP Runway 9C-27C East Package - ORD, Spec 163099 06/05/2019 OHARE MODERNIZATION PROJECT $13,047.10
OMP Runway 9C-27C East Package - ORD, Spec 163099 06/10/2019 OHARE MODERNIZATION PROJECT $127,631.54
OMP Runway 9C-27C East Package - ORD, Spec 163099 06/13/2019 OHARE MODERNIZATION PROJECT ($817,344.70)
4156796
OMP Runway 9C-27C East Package - ORD, Spec 163099 07/02/2019 OHARE MODERNIZATION PROJECT $839,717.76
4156798
OMP Runway 9C-27C East Package - ORD, Spec 163099 07/25/2019 OHARE MODERNIZATION PROJECT $9,980.46
4156799
OMP Runway 9C-27C East Package - ORD, Spec 163099 07/29/2019 OHARE MODERNIZATION PROJECT ($17,359.39)