06/27/2014 | DEPARTMENT OF WATER MANAGEMENT | $2,536,520.00 |
Modification # | Description | Disclosure # | Award Date | Start Date | End Date | Department | Amount |
---|---|---|---|---|---|---|---|
3025410
| S. Escanaba Ave. Sewer Improvement Project | 05/19/2016 | DEPARTMENT OF WATER MANAGEMENT | ($265,243.83) | |||
S. Escanaba Ave. Sewer Improvement Project | 06/15/2016 | DEPARTMENT OF WATER MANAGEMENT | $3,437.82 | ||||
3025412
| S. Escanaba Ave. Sewer Improvement Project | 10/20/2016 | DEPARTMENT OF WATER MANAGEMENT | $3,363.60 | |||
S. Escanaba Ave. Sewer Improvement Project | 04/26/2017 | DEPARTMENT OF WATER MANAGEMENT | ($207,349.81) | ||||
S. Escanaba Ave. Sewer Improvement Project | 10/17/2014 | DEPARTMENT OF WATER MANAGEMENT | $18,800.00 | ||||
302543
| S. Escanaba Ave. Sewer Improvement Project | 11/25/2014 | DEPARTMENT OF WATER MANAGEMENT | $15,625.00 | |||
302544
| S. Escanaba Ave. Sewer Improvement Project | 12/16/2014 | DEPARTMENT OF WATER MANAGEMENT | $52,800.00 | |||
S. Escanaba Ave. Sewer Improvement Project | 01/13/2015 | DEPARTMENT OF WATER MANAGEMENT | $328,000.00 | ||||
S. Escanaba Ave. Sewer Improvement Project | 01/14/2015 | DEPARTMENT OF WATER MANAGEMENT | $29,066.19 | ||||
302547
| S. Escanaba Ave. Sewer Improvement Project | 01/20/2015 | DEPARTMENT OF WATER MANAGEMENT | $9,000.00 | |||