Contract (PO) # Disclosure # Award Date Start Date End Date Department Original Award Amount
06/01/2011 OHARE MODERNIZATION PROJECT $36,761,303.39

Modifications/Amendments

Modification # Description Disclosure # Award Date Start Date End Date Department Amount
246411
RUNWAY 9C-27C NORTHEAST PACKAGE 07/14/2011 OHARE MODERNIZATION PROJECT $14,884.00
RUNWAY 9C-27C NORTHEAST PACKAGE 09/14/2011 OHARE MODERNIZATION PROJECT $50,000.00
RUNWAY 9C-27C NORTHEAST PACKAGE 11/23/2012 OHARE MODERNIZATION PROJECT $49,053.00
24641101
RUNWAY 9C-27C NORTHEAST PACKAGE 11/28/2012 OHARE MODERNIZATION PROJECT $290,468.64
RUNWAY 9C-27C NORTHEAST PACKAGE 12/04/2012 OHARE MODERNIZATION PROJECT $52,187.00
RUNWAY 9C-27C NORTHEAST PACKAGE 12/05/2012 OHARE MODERNIZATION PROJECT ($173,408.08)
24641104
RUNWAY 9C-27C NORTHEAST PACKAGE 12/06/2012 OHARE MODERNIZATION PROJECT ($101,498.94)
RUNWAY 9C-27C NORTHEAST PACKAGE 12/10/2012 OHARE MODERNIZATION PROJECT $41,675.63
RUNWAY 9C-27C NORTHEAST PACKAGE 12/12/2012 OHARE MODERNIZATION PROJECT $36,623.00
RUNWAY 9C-27C NORTHEAST PACKAGE 12/17/2012 OHARE MODERNIZATION PROJECT $230,000.00
RUNWAY 9C-27C NORTHEAST PACKAGE 12/19/2012 OHARE MODERNIZATION PROJECT $30,884.00
24641109
RUNWAY 9C-27C NORTHEAST PACKAGE 12/26/2012 OHARE MODERNIZATION PROJECT ($1,149,126.75)
RUNWAY 9C-27C NORTHEAST PACKAGE 09/15/2011 OHARE MODERNIZATION PROJECT $20,000.00
RUNWAY 9C-27C NORTHEAST PACKAGE 12/28/2012 OHARE MODERNIZATION PROJECT $78,542.00
RUNWAY 9C-27C NORTHEAST PACKAGE 01/08/2013 OHARE MODERNIZATION PROJECT $38,471.45
RUNWAY 9C-27C NORTHEAST PACKAGE 01/08/2013 OHARE MODERNIZATION PROJECT $1,331.90
RUNWAY 9C-27C NORTHEAST PACKAGE 01/09/2013 OHARE MODERNIZATION PROJECT ($81,737.48)
24641114
RUNWAY 9C-27C NORTHEAST PACKAGE 01/11/2013 OHARE MODERNIZATION PROJECT $241,031.37
24641115
RUNWAY 9C-27C NORTHEAST PACKAGE 01/16/2013 OHARE MODERNIZATION PROJECT ($240,731.66)
RUNWAY 9C-27C NORTHEAST PACKAGE 02/07/2013 OHARE MODERNIZATION PROJECT ($19,304.87)
RUNWAY 9C-27C NORTHEAST PACKAGE 02/21/2013 OHARE MODERNIZATION PROJECT ($65,360.96)
RUNWAY 9C-27C NORTHEAST PACKAGE 03/22/2013 OHARE MODERNIZATION PROJECT $107,174.00
24641119
RUNWAY 9C-27C NORTHEAST PACKAGE 05/09/2013 OHARE MODERNIZATION PROJECT $14,964.00
RUNWAY 9C-27C NORTHEAST PACKAGE 09/16/2011 OHARE MODERNIZATION PROJECT $111,193.00
RUNWAY 9C-27C NORTHEAST PACKAGE 05/24/2013 OHARE MODERNIZATION PROJECT $103,362.62
RUNWAY 9C-27C NORTHEAST PACKAGE 07/03/2013 OHARE MODERNIZATION PROJECT $180,654.16
24641122
RUNWAY 9C-27C NORTHEAST PACKAGE 08/21/2013 OHARE MODERNIZATION PROJECT $29,123.15
RUNWAY 9C-27C NORTHEAST PACKAGE 09/16/2011 OHARE MODERNIZATION PROJECT ($48,187.50)
2464114
RUNWAY 9C-27C NORTHEAST PACKAGE 09/19/2011 OHARE MODERNIZATION PROJECT $150,979.49
2464115
RUNWAY 9C-27C NORTHEAST PACKAGE 09/20/2011 OHARE MODERNIZATION PROJECT $4,090.00
2464116
RUNWAY 9C-27C NORTHEAST PACKAGE 09/21/2011 OHARE MODERNIZATION PROJECT ($319,110.36)
2464117
RUNWAY 9C-27C NORTHEAST PACKAGE 09/27/2011 OHARE MODERNIZATION PROJECT $912,742.00
2464118
RUNWAY 9C-27C NORTHEAST PACKAGE 09/27/2011 OHARE MODERNIZATION PROJECT ($911,131.40)
2464119
RUNWAY 9C-27C NORTHEAST PACKAGE 10/19/2011 OHARE MODERNIZATION PROJECT $397,500.00
246412
RUNWAY 9C-27C NORTHEAST PACKAGE 08/10/2011 OHARE MODERNIZATION PROJECT $28,160.00
RUNWAY 9C-27C NORTHEAST PACKAGE 10/21/2011 OHARE MODERNIZATION PROJECT $150,000.00
2464121
RUNWAY 9C-27C NORTHEAST PACKAGE 10/24/2011 OHARE MODERNIZATION PROJECT ($60,451.35)
2464122
RUNWAY 9C-27C NORTHEAST PACKAGE 10/25/2011 OHARE MODERNIZATION PROJECT $501,458.44
2464123
RUNWAY 9C-27C NORTHEAST PACKAGE 10/28/2011 OHARE MODERNIZATION PROJECT $27,415.00
2464124
RUNWAY 9C-27C NORTHEAST PACKAGE 10/31/2011 OHARE MODERNIZATION PROJECT ($655,902.62)
RUNWAY 9C-27C NORTHEAST PACKAGE 10/31/2011 OHARE MODERNIZATION PROJECT $188,000.00
2464126
RUNWAY 9C-27C NORTHEAST PACKAGE 11/02/2011 OHARE MODERNIZATION PROJECT $167,630.00
2464127
RUNWAY 9C-27C NORTHEAST PACKAGE 11/03/2011 OHARE MODERNIZATION PROJECT ($100,090.00)
2464128
RUNWAY 9C-27C NORTHEAST PACKAGE 11/04/2011 OHARE MODERNIZATION PROJECT $214,885.00
2464129
RUNWAY 9C-27C NORTHEAST PACKAGE 11/07/2011 OHARE MODERNIZATION PROJECT ($144,606.00)
246413
RUNWAY 9C-27C NORTHEAST PACKAGE 08/10/2011 OHARE MODERNIZATION PROJECT $96,500.00
RUNWAY 9C-27C NORTHEAST PACKAGE 11/07/2011 OHARE MODERNIZATION PROJECT $25,000.00
RUNWAY 9C-27C NORTHEAST PACKAGE 11/16/2011 OHARE MODERNIZATION PROJECT $36,496.00
RUNWAY 9C-27C NORTHEAST PACKAGE 11/17/2011 OHARE MODERNIZATION PROJECT $160,000.00
RUNWAY 9C-27C NORTHEAST PACKAGE 11/28/2011 OHARE MODERNIZATION PROJECT $378,100.00
2464134
RUNWAY 9C-27C NORTHEAST PACKAGE 11/29/2011 OHARE MODERNIZATION PROJECT ($31,747.00)
2464135
RUNWAY 9C-27C NORTHEAST PACKAGE 11/29/2011 OHARE MODERNIZATION PROJECT $81,223.90
RUNWAY 9C-27C NORTHEAST PACKAGE 12/05/2011 OHARE MODERNIZATION PROJECT $1,448.50
2464137
RUNWAY 9C-27C NORTHEAST PACKAGE 12/12/2011 OHARE MODERNIZATION PROJECT ($600.00)
2464138
RUNWAY 9C-27C NORTHEAST PACKAGE 12/14/2011 OHARE MODERNIZATION PROJECT $72,694.00
2464139
RUNWAY 9C-27C NORTHEAST PACKAGE 12/15/2011 OHARE MODERNIZATION PROJECT $22,155.00
246414
RUNWAY 9C-27C NORTHEAST PACKAGE 08/10/2011 OHARE MODERNIZATION PROJECT $3,937.50
2464140
RUNWAY 9C-27C NORTHEAST PACKAGE 12/20/2011 OHARE MODERNIZATION PROJECT $8,935.00
2464141
RUNWAY 9C-27C NORTHEAST PACKAGE 01/06/2012 OHARE MODERNIZATION PROJECT $79,877.92
RUNWAY 9C-27C NORTHEAST PACKAGE 01/11/2012 OHARE MODERNIZATION PROJECT $312,824.00
2464143
RUNWAY 9C-27C NORTHEAST PACKAGE 01/12/2012 OHARE MODERNIZATION PROJECT ($4,595.15)
2464144
RUNWAY 9C-27C NORTHEAST PACKAGE 01/12/2012 OHARE MODERNIZATION PROJECT ($418,231.87)
RUNWAY 9C-27C NORTHEAST PACKAGE 01/12/2012 OHARE MODERNIZATION PROJECT $19,552.00
RUNWAY 9C-27C NORTHEAST PACKAGE 01/27/2012 OHARE MODERNIZATION PROJECT $1,591,528.00
RUNWAY 9C-27C NORTHEAST PACKAGE 01/27/2012 OHARE MODERNIZATION PROJECT $750,000.00
RUNWAY 9C-27C NORTHEAST PACKAGE 01/27/2012 OHARE MODERNIZATION PROJECT $13,657.00
246415
RUNWAY 9C-27C NORTHEAST PACKAGE 08/11/2011 OHARE MODERNIZATION PROJECT $2,520.00
RUNWAY 9C-27C NORTHEAST PACKAGE 01/30/2012 OHARE MODERNIZATION PROJECT $44,687.00
RUNWAY 9C-27C NORTHEAST PACKAGE 01/31/2012 OHARE MODERNIZATION PROJECT $94,926.00
2464152
RUNWAY 9C-27C NORTHEAST PACKAGE 02/06/2012 OHARE MODERNIZATION PROJECT $363,620.49
RUNWAY 9C-27C NORTHEAST PACKAGE 02/08/2012 OHARE MODERNIZATION PROJECT $13,660.00
2464155
RUNWAY 9C-27C NORTHEAST PACKAGE 02/15/2012 OHARE MODERNIZATION PROJECT ($75,384.60)
2464156
RUNWAY 9C-27C NORTHEAST PACKAGE 02/16/2012 OHARE MODERNIZATION PROJECT $180,527.00
RUNWAY 9C-27C NORTHEAST PACKAGE 02/21/2012 OHARE MODERNIZATION PROJECT $100,000.00
2464158
RUNWAY 9C-27C NORTHEAST PACKAGE 02/24/2012 OHARE MODERNIZATION PROJECT $6,543.00
RUNWAY 9C-27C NORTHEAST PACKAGE 02/28/2012 OHARE MODERNIZATION PROJECT $90,500.00
246416
RUNWAY 9C-27C NORTHEAST PACKAGE 08/11/2011 OHARE MODERNIZATION PROJECT $73,740.00
2464160
RUNWAY 9C-27C NORTHEAST PACKAGE 03/13/2012 OHARE MODERNIZATION PROJECT ($10,500.00)
2464161
RUNWAY 9C-27C NORTHEAST PACKAGE 03/16/2012 OHARE MODERNIZATION PROJECT ($13,603.00)
RUNWAY 9C-27C NORTHEAST PACKAGE 03/29/2012 OHARE MODERNIZATION PROJECT $10,500.00
RUNWAY 9C-27C NORTHEAST PACKAGE 04/19/2012 OHARE MODERNIZATION PROJECT $9,756.00
2464164
RUNWAY 9C-27C NORTHEAST PACKAGE 04/27/2012 OHARE MODERNIZATION PROJECT ($778,383.94)
2464165
RUNWAY 9C-27C NORTHEAST PACKAGE 05/04/2012 OHARE MODERNIZATION PROJECT $270,011.40
RUNWAY 9C-27C NORTHEAST PACKAGE 05/08/2012 OHARE MODERNIZATION PROJECT $550,000.00
RUNWAY 9C-27C NORTHEAST PACKAGE 05/10/2012 OHARE MODERNIZATION PROJECT $72,306.06
RUNWAY 9C-27C NORTHEAST PACKAGE 05/23/2012 OHARE MODERNIZATION PROJECT $12,409.00
RUNWAY 9C-27C NORTHEAST PACKAGE 09/07/2011 OHARE MODERNIZATION PROJECT $2,800.00
RUNWAY 9C-27C NORTHEAST PACKAGE 05/30/2012 OHARE MODERNIZATION PROJECT ($25,000.00)
RUNWAY 9C-27C NORTHEAST PACKAGE 05/31/2012 OHARE MODERNIZATION PROJECT ($96,651.71)
RUNWAY 9C-27C NORTHEAST PACKAGE 06/01/2012 OHARE MODERNIZATION PROJECT $14,050.00
2464173
RUNWAY 9C-27C NORTHEAST PACKAGE 06/11/2012 OHARE MODERNIZATION PROJECT ($6,187.50)
RUNWAY 9C-27C NORTHEAST PACKAGE 06/15/2012 OHARE MODERNIZATION PROJECT $43,000.00
2464175
RUNWAY 9C-27C NORTHEAST PACKAGE 06/15/2012 OHARE MODERNIZATION PROJECT ($0.03)
2464176
RUNWAY 9C-27C NORTHEAST PACKAGE 06/25/2012 OHARE MODERNIZATION PROJECT $160,250.01
2464177
RUNWAY 9C-27C NORTHEAST PACKAGE 07/03/2012 OHARE MODERNIZATION PROJECT $3,337.85
2464178
RUNWAY 9C-27C NORTHEAST PACKAGE 07/09/2012 OHARE MODERNIZATION PROJECT ($69,475.45)
2464179
RUNWAY 9C-27C NORTHEAST PACKAGE 07/17/2012 OHARE MODERNIZATION PROJECT $143,100.00
RUNWAY 9C-27C NORTHEAST PACKAGE 09/08/2011 OHARE MODERNIZATION PROJECT $16,841.00
RUNWAY 9C-27C NORTHEAST PACKAGE 07/30/2012 OHARE MODERNIZATION PROJECT $40,000.00
RUNWAY 9C-27C NORTHEAST PACKAGE 08/02/2012 OHARE MODERNIZATION PROJECT $1,624.00
RUNWAY 9C-27C NORTHEAST PACKAGE 08/06/2012 OHARE MODERNIZATION PROJECT $23,293.00
RUNWAY 9C-27C NORTHEAST PACKAGE 08/08/2012 OHARE MODERNIZATION PROJECT $23,067.00
RUNWAY 9C-27C NORTHEAST PACKAGE 08/20/2012 OHARE MODERNIZATION PROJECT $804,433.00
2464185
RUNWAY 9C-27C NORTHEAST PACKAGE 08/27/2012 OHARE MODERNIZATION PROJECT $46,282.07
RUNWAY 9C-27C NORTHEAST PACKAGE 08/29/2012 OHARE MODERNIZATION PROJECT $25,000.00
2464187
RUNWAY 9C-27C NORTHEAST PACKAGE 09/07/2012 OHARE MODERNIZATION PROJECT ($46,200.00)
2464188
RUNWAY 9C-27C NORTHEAST PACKAGE 09/17/2012 OHARE MODERNIZATION PROJECT $5,007.00
2464189
RUNWAY 9C-27C NORTHEAST PACKAGE 09/19/2012 OHARE MODERNIZATION PROJECT $194,651.06
RUNWAY 9C-27C NORTHEAST PACKAGE 09/09/2011 OHARE MODERNIZATION PROJECT $9,520.00
RUNWAY 9C-27C NORTHEAST PACKAGE 09/25/2012 OHARE MODERNIZATION PROJECT $497,826.00
RUNWAY 9C-27C NORTHEAST PACKAGE 09/27/2012 OHARE MODERNIZATION PROJECT ($85,000.00)
RUNWAY 9C-27C NORTHEAST PACKAGE 10/02/2012 OHARE MODERNIZATION PROJECT $346,072.00
2464193
RUNWAY 9C-27C NORTHEAST PACKAGE 10/09/2012 OHARE MODERNIZATION PROJECT $101,498.94
RUNWAY 9C-27C NORTHEAST PACKAGE 10/25/2012 OHARE MODERNIZATION PROJECT $30,807.00
RUNWAY 9C-27C NORTHEAST PACKAGE 10/29/2012 OHARE MODERNIZATION PROJECT $75,000.00
2464197
RUNWAY 9C-27C NORTHEAST PACKAGE 11/08/2012 OHARE MODERNIZATION PROJECT $257,161.00
RUNWAY 9C-27C NORTHEAST PACKAGE 11/14/2012 OHARE MODERNIZATION PROJECT $92,556.89
2464199
RUNWAY 9C-27C NORTHEAST PACKAGE 11/19/2012 OHARE MODERNIZATION PROJECT ($131,565.76)