DUR in the Award Amount column means that the contract award total Depends Upon Requirements. A Depends Upon Requirements contract is an indefinite quantities contract in which the city places orders as needed. The vendor is not guaranteed any particular contract award amount.
Contract (PO) # Disclosure # Award Date Start Date End Date Original Award Amount
09/23/2009 $12,591,851.60

Modifications/Amendments

Modification # Description Disclosure # Award Date Start Date End Date Amount
205111
MILWAUKEE AVENUE SECTION 2 - SIX CORNERS IMPROVEMENTS 10/23/2009 $0.00
MILWAUKEE AVENUE SECTION 2 - SIX CORNERS IMPROVEMENTS 04/29/2011 ($668.89)
MILWAUKEE AVENUE SECTION 2 - SIX CORNERS IMPROVEMENTS 10/10/2011 ($1,849.17)
MILWAUKEE AVENUE SECTION 2 - SIX CORNERS IMPROVEMENTS 03/12/2012 $13,500.00
MILWAUKEE AVENUE SECTION 2 - SIX CORNERS IMPROVEMENTS 04/13/2012 $132.50
MILWAUKEE AVENUE SECTION 2 - SIX CORNERS IMPROVEMENTS 04/17/2012 ($1,761.35)
MILWAUKEE AVENUE SECTION 2 - SIX CORNERS IMPROVEMENTS 06/20/2012 $32,500.00
MILWAUKEE AVENUE SECTION 2 - SIX CORNERS IMPROVEMENTS 06/21/2012 $13,000.00
2051117
MILWAUKEE AVENUE SECTION 2 - SIX CORNERS IMPROVEMENTS 06/29/2012 ($685,568.82)
MILWAUKEE AVENUE SECTION 2 - SIX CORNERS IMPROVEMENTS 07/02/2012 ($4,789.48)
MILWAUKEE AVENUE SECTION 2 - SIX CORNERS IMPROVEMENTS 07/03/2012 $3,302.63
MILWAUKEE AVENUE SECTION 2 - SIX CORNERS IMPROVEMENTS 08/13/2010 $77,000.00
MILWAUKEE AVENUE SECTION 2 - SIX CORNERS IMPROVEMENTS 07/06/2012 $1,263.17
MILWAUKEE AVENUE SECTION 2 - SIX CORNERS IMPROVEMENTS 07/09/2012 ($205.30)
MILWAUKEE AVENUE SECTION 2 - SIX CORNERS IMPROVEMENTS 07/11/2012 $775.87
MILWAUKEE AVENUE SECTION 2 - SIX CORNERS IMPROVEMENTS 07/26/2012 $1,880.00
MILWAUKEE AVENUE SECTION 2 - SIX CORNERS IMPROVEMENTS 10/23/2012 $4,718.80
2051125
MILWAUKEE AVENUE SECTION 2 - SIX CORNERS IMPROVEMENTS 01/06/2016 $175,310.27
2051126
MILWAUKEE AVENUE SECTION 2 - SIX CORNERS IMPROVEMENTS 05/06/2016 ($65.29)
2051127
MILWAUKEE AVENUE SECTION 2 - SIX CORNERS IMPROVEMENTS 01/15/2019 $642,224.95
2051128
MILWAUKEE AVENUE SECTION 2 - SIX CORNERS IMPROVEMENTS 03/14/2019 ($642,224.94)
MILWAUKEE AVENUE SECTION 2 - SIX CORNERS IMPROVEMENTS 08/17/2010 $28,500.00
205114
MILWAUKEE AVENUE SECTION 2 - SIX CORNERS IMPROVEMENTS 09/14/2010 $174,420.00
205115
MILWAUKEE AVENUE SECTION 2 - SIX CORNERS IMPROVEMENTS 03/09/2011 $70,195.00
205116
MILWAUKEE AVENUE SECTION 2 - SIX CORNERS IMPROVEMENTS 03/10/2011 $1,888.03
MILWAUKEE AVENUE SECTION 2 - SIX CORNERS IMPROVEMENTS 03/11/2011 $30,000.00
MILWAUKEE AVENUE SECTION 2 - SIX CORNERS IMPROVEMENTS 04/12/2011 ($385.29)