Contract (PO) # Disclosure # Award Date Start Date End Date Department Original Award Amount
03/13/2009 OHARE MODERNIZATION PROJECT $139,546,855.52

Modifications/Amendments

Modification # Description Disclosure # Award Date Start Date End Date Department Amount
RUNWAY 10C-28C EAST AND TAXIWAYS, SPEC. 69501 06/24/2009 OHARE MODERNIZATION PROJECT ($175,000.00)
RUNWAY 10C-28C EAST AND TAXIWAYS, SPEC. 69501 07/20/2010 OHARE MODERNIZATION PROJECT $65,766.88
RUNWAY 10C-28C EAST AND TAXIWAYS, SPEC. 69501 07/22/2010 OHARE MODERNIZATION PROJECT $21,210.40
19486102
RUNWAY 10C-28C EAST AND TAXIWAYS, SPEC. 69501 07/27/2010 OHARE MODERNIZATION PROJECT $6,536.80
19486103
RUNWAY 10C-28C EAST AND TAXIWAYS, SPEC. 69501 07/29/2010 OHARE MODERNIZATION PROJECT ($184,260.00)
19486104
RUNWAY 10C-28C EAST AND TAXIWAYS, SPEC. 69501 08/11/2010 OHARE MODERNIZATION PROJECT ($5,605,050.00)
19486105
RUNWAY 10C-28C EAST AND TAXIWAYS, SPEC. 69501 08/24/2010 OHARE MODERNIZATION PROJECT ($1,271,426.00)
19486106
RUNWAY 10C-28C EAST AND TAXIWAYS, SPEC. 69501 08/31/2010 OHARE MODERNIZATION PROJECT $1,863,749.88
19486107
RUNWAY 10C-28C EAST AND TAXIWAYS, SPEC. 69501 09/03/2010 OHARE MODERNIZATION PROJECT ($44,499.00)
RUNWAY 10C-28C EAST AND TAXIWAYS, SPEC. 69501 09/14/2010 OHARE MODERNIZATION PROJECT $700,000.00
RUNWAY 10C-28C EAST AND TAXIWAYS, SPEC. 69501 09/15/2010 OHARE MODERNIZATION PROJECT $113,185.00
1948611
RUNWAY 10C-28C EAST AND TAXIWAYS, SPEC. 69501 07/01/2009 OHARE MODERNIZATION PROJECT $1,985,719.91
RUNWAY 10C-28C EAST AND TAXIWAYS, SPEC. 69501 09/20/2010 OHARE MODERNIZATION PROJECT $174,140.00
RUNWAY 10C-28C EAST AND TAXIWAYS, SPEC. 69501 09/22/2010 OHARE MODERNIZATION PROJECT $49,000.00
RUNWAY 10C-28C EAST AND TAXIWAYS, SPEC. 69501 09/29/2010 OHARE MODERNIZATION PROJECT $2,500.00
19486113
RUNWAY 10C-28C EAST AND TAXIWAYS, SPEC. 69501 10/06/2010 OHARE MODERNIZATION PROJECT $279,890.50
19486114
RUNWAY 10C-28C EAST AND TAXIWAYS, SPEC. 69501 10/08/2010 OHARE MODERNIZATION PROJECT ($278,080.00)
19486115
RUNWAY 10C-28C EAST AND TAXIWAYS, SPEC. 69501 10/18/2010 OHARE MODERNIZATION PROJECT ($15,142.37)
19486116
RUNWAY 10C-28C EAST AND TAXIWAYS, SPEC. 69501 10/19/2010 OHARE MODERNIZATION PROJECT $500,000.00
19486117
RUNWAY 10C-28C EAST AND TAXIWAYS, SPEC. 69501 10/21/2010 OHARE MODERNIZATION PROJECT $1,768,460.00
RUNWAY 10C-28C EAST AND TAXIWAYS, SPEC. 69501 11/23/2010 OHARE MODERNIZATION PROJECT $2,237,475.00
RUNWAY 10C-28C EAST AND TAXIWAYS, SPEC. 69501 12/06/2010 OHARE MODERNIZATION PROJECT $56,000.00
RUNWAY 10C-28C EAST AND TAXIWAYS, SPEC. 69501 07/09/2009 OHARE MODERNIZATION PROJECT $111,981.00
19486120
RUNWAY 10C-28C EAST AND TAXIWAYS, SPEC. 69501 12/22/2010 OHARE MODERNIZATION PROJECT ($2,603,160.92)
19486121
RUNWAY 10C-28C EAST AND TAXIWAYS, SPEC. 69501 12/28/2010 OHARE MODERNIZATION PROJECT $52,400.00
19486122
RUNWAY 10C-28C EAST AND TAXIWAYS, SPEC. 69501 01/10/2011 OHARE MODERNIZATION PROJECT ($806,520.00)
19486123
RUNWAY 10C-28C EAST AND TAXIWAYS, SPEC. 69501 01/20/2011 OHARE MODERNIZATION PROJECT $165,972.89
19486124
RUNWAY 10C-28C EAST AND TAXIWAYS, SPEC. 69501 01/27/2011 OHARE MODERNIZATION PROJECT ($75,984.80)
19486125
RUNWAY 10C-28C EAST AND TAXIWAYS, SPEC. 69501 02/13/2011 OHARE MODERNIZATION PROJECT $113,676.00
RUNWAY 10C-28C EAST AND TAXIWAYS, SPEC. 69501 02/21/2011 OHARE MODERNIZATION PROJECT $2,400,000.00
RUNWAY 10C-28C EAST AND TAXIWAYS, SPEC. 69501 02/23/2011 OHARE MODERNIZATION PROJECT $2,784,000.00
19486129
RUNWAY 10C-28C EAST AND TAXIWAYS, SPEC. 69501 02/25/2011 OHARE MODERNIZATION PROJECT $714,142.20
RUNWAY 10C-28C EAST AND TAXIWAYS, SPEC. 69501 07/16/2009 OHARE MODERNIZATION PROJECT $21,787.00
19486130
RUNWAY 10C-28C EAST AND TAXIWAYS, SPEC. 69501 03/01/2011 OHARE MODERNIZATION PROJECT $231,480.00
19486131
RUNWAY 10C-28C EAST AND TAXIWAYS, SPEC. 69501 03/10/2011 OHARE MODERNIZATION PROJECT $71,950.00
RUNWAY 10C-28C EAST AND TAXIWAYS, SPEC. 69501 03/22/2011 OHARE MODERNIZATION PROJECT $750,000.00
19486133
RUNWAY 10C-28C EAST AND TAXIWAYS, SPEC. 69501 03/25/2011 OHARE MODERNIZATION PROJECT $3,500.00
19486134
RUNWAY 10C-28C EAST AND TAXIWAYS, SPEC. 69501 04/12/2011 OHARE MODERNIZATION PROJECT ($18,780.00)
19486135
RUNWAY 10C-28C EAST AND TAXIWAYS, SPEC. 69501 04/26/2011 OHARE MODERNIZATION PROJECT ($72,575.00)
RUNWAY 10C-28C EAST AND TAXIWAYS, SPEC. 69501 05/03/2011 OHARE MODERNIZATION PROJECT $7,985.00
RUNWAY 10C-28C EAST AND TAXIWAYS, SPEC. 69501 05/10/2011 OHARE MODERNIZATION PROJECT $20,325.00
RUNWAY 10C-28C EAST AND TAXIWAYS, SPEC. 69501 05/13/2011 OHARE MODERNIZATION PROJECT ($37,500.00)
RUNWAY 10C-28C EAST AND TAXIWAYS, SPEC. 69501 05/24/2011 OHARE MODERNIZATION PROJECT ($33,000.00)
1948614
RUNWAY 10C-28C EAST AND TAXIWAYS, SPEC. 69501 07/21/2009 OHARE MODERNIZATION PROJECT $620,025.00
19486140
RUNWAY 10C-28C EAST AND TAXIWAYS, SPEC. 69501 05/26/2011 OHARE MODERNIZATION PROJECT $11,250.00
19486141
RUNWAY 10C-28C EAST AND TAXIWAYS, SPEC. 69501 06/02/2011 OHARE MODERNIZATION PROJECT ($18,700.00)
RUNWAY 10C-28C EAST AND TAXIWAYS, SPEC. 69501 06/17/2011 OHARE MODERNIZATION PROJECT $750,000.00
19486143
RUNWAY 10C-28C EAST AND TAXIWAYS, SPEC. 69501 06/27/2011 OHARE MODERNIZATION PROJECT $70,490.00
19486144
RUNWAY 10C-28C EAST AND TAXIWAYS, SPEC. 69501 07/08/2011 OHARE MODERNIZATION PROJECT $757,429.24
19486145
RUNWAY 10C-28C EAST AND TAXIWAYS, SPEC. 69501 07/13/2011 OHARE MODERNIZATION PROJECT $12,445.50
19486146
RUNWAY 10C-28C EAST AND TAXIWAYS, SPEC. 69501 07/14/2011 OHARE MODERNIZATION PROJECT ($89,046.00)
19486147
RUNWAY 10C-28C EAST AND TAXIWAYS, SPEC. 69501 07/20/2011 OHARE MODERNIZATION PROJECT $42,340.00
RUNWAY 10C-28C EAST AND TAXIWAYS, SPEC. 69501 07/20/2011 OHARE MODERNIZATION PROJECT $2,948,628.00
19486149
RUNWAY 10C-28C EAST AND TAXIWAYS, SPEC. 69501 07/20/2011 OHARE MODERNIZATION PROJECT $1,368,196.69
RUNWAY 10C-28C EAST AND TAXIWAYS, SPEC. 69501 07/30/2009 OHARE MODERNIZATION PROJECT $8,030.00
RUNWAY 10C-28C EAST AND TAXIWAYS, SPEC. 69501 07/20/2011 OHARE MODERNIZATION PROJECT $867,207.00
RUNWAY 10C-28C EAST AND TAXIWAYS, SPEC. 69501 07/20/2011 OHARE MODERNIZATION PROJECT $658,558.00
19486152
RUNWAY 10C-28C EAST AND TAXIWAYS, SPEC. 69501 07/20/2011 OHARE MODERNIZATION PROJECT $594,358.21
RUNWAY 10C-28C EAST AND TAXIWAYS, SPEC. 69501 07/20/2011 OHARE MODERNIZATION PROJECT $414,800.00
RUNWAY 10C-28C EAST AND TAXIWAYS, SPEC. 69501 07/20/2011 OHARE MODERNIZATION PROJECT $58,000.00
19486155
RUNWAY 10C-28C EAST AND TAXIWAYS, SPEC. 69501 07/21/2011 OHARE MODERNIZATION PROJECT $138,280.90
RUNWAY 10C-28C EAST AND TAXIWAYS, SPEC. 69501 07/21/2011 OHARE MODERNIZATION PROJECT $200,000.00
19486157
RUNWAY 10C-28C EAST AND TAXIWAYS, SPEC. 69501 07/21/2011 OHARE MODERNIZATION PROJECT $199,065.14
RUNWAY 10C-28C EAST AND TAXIWAYS, SPEC. 69501 07/21/2011 OHARE MODERNIZATION PROJECT $286,710.00
RUNWAY 10C-28C EAST AND TAXIWAYS, SPEC. 69501 07/21/2011 OHARE MODERNIZATION PROJECT $270,000.00
RUNWAY 10C-28C EAST AND TAXIWAYS, SPEC. 69501 08/24/2009 OHARE MODERNIZATION PROJECT $165,000.00
RUNWAY 10C-28C EAST AND TAXIWAYS, SPEC. 69501 07/21/2011 OHARE MODERNIZATION PROJECT $218,500.00
RUNWAY 10C-28C EAST AND TAXIWAYS, SPEC. 69501 07/21/2011 OHARE MODERNIZATION PROJECT $230,000.00
RUNWAY 10C-28C EAST AND TAXIWAYS, SPEC. 69501 07/21/2011 OHARE MODERNIZATION PROJECT $114,000.00
RUNWAY 10C-28C EAST AND TAXIWAYS, SPEC. 69501 07/21/2011 OHARE MODERNIZATION PROJECT $150,000.00
RUNWAY 10C-28C EAST AND TAXIWAYS, SPEC. 69501 07/21/2011 OHARE MODERNIZATION PROJECT $96,000.00
RUNWAY 10C-28C EAST AND TAXIWAYS, SPEC. 69501 07/22/2011 OHARE MODERNIZATION PROJECT ($189,700.00)
RUNWAY 10C-28C EAST AND TAXIWAYS, SPEC. 69501 07/22/2011 OHARE MODERNIZATION PROJECT $22,300.00
RUNWAY 10C-28C EAST AND TAXIWAYS, SPEC. 69501 07/22/2011 OHARE MODERNIZATION PROJECT $22,000.00
19486168
RUNWAY 10C-28C EAST AND TAXIWAYS, SPEC. 69501 07/22/2011 OHARE MODERNIZATION PROJECT $783.25
19486169
RUNWAY 10C-28C EAST AND TAXIWAYS, SPEC. 69501 07/22/2011 OHARE MODERNIZATION PROJECT $42,500.00
RUNWAY 10C-28C EAST AND TAXIWAYS, SPEC. 69501 08/28/2009 OHARE MODERNIZATION PROJECT $27,500.00
RUNWAY 10C-28C EAST AND TAXIWAYS, SPEC. 69501 07/22/2011 OHARE MODERNIZATION PROJECT $63,327.00
RUNWAY 10C-28C EAST AND TAXIWAYS, SPEC. 69501 07/25/2011 OHARE MODERNIZATION PROJECT $24,364.70
19486172
RUNWAY 10C-28C EAST AND TAXIWAYS, SPEC. 69501 07/25/2011 OHARE MODERNIZATION PROJECT ($72,000.00)
19486173
RUNWAY 10C-28C EAST AND TAXIWAYS, SPEC. 69501 07/25/2011 OHARE MODERNIZATION PROJECT ($123,498.00)
RUNWAY 10C-28C EAST AND TAXIWAYS, SPEC. 69501 07/26/2011 OHARE MODERNIZATION PROJECT $1,940.00
RUNWAY 10C-28C EAST AND TAXIWAYS, SPEC. 69501 07/26/2011 OHARE MODERNIZATION PROJECT $33,814.72
19486177
RUNWAY 10C-28C EAST AND TAXIWAYS, SPEC. 69501 07/26/2011 OHARE MODERNIZATION PROJECT $114,481.87
RUNWAY 10C-28C EAST AND TAXIWAYS, SPEC. 69501 07/26/2011 OHARE MODERNIZATION PROJECT $4,055.89
19486179
RUNWAY 10C-28C EAST AND TAXIWAYS, SPEC. 69501 07/26/2011 OHARE MODERNIZATION PROJECT $13,520.00
1948618
RUNWAY 10C-28C EAST AND TAXIWAYS, SPEC. 69501 09/23/2009 OHARE MODERNIZATION PROJECT $134,560.00
19486181
RUNWAY 10C-28C EAST AND TAXIWAYS, SPEC. 69501 07/27/2011 OHARE MODERNIZATION PROJECT ($141,860.42)
19486182
RUNWAY 10C-28C EAST AND TAXIWAYS, SPEC. 69501 07/27/2011 OHARE MODERNIZATION PROJECT $59,555.25
RUNWAY 10C-28C EAST AND TAXIWAYS, SPEC. 69501 07/27/2011 OHARE MODERNIZATION PROJECT $41,900.00
19486184
RUNWAY 10C-28C EAST AND TAXIWAYS, SPEC. 69501 07/27/2011 OHARE MODERNIZATION PROJECT $30,981.50
19486185
RUNWAY 10C-28C EAST AND TAXIWAYS, SPEC. 69501 07/27/2011 OHARE MODERNIZATION PROJECT $50,568.18
19486186
RUNWAY 10C-28C EAST AND TAXIWAYS, SPEC. 69501 07/27/2011 OHARE MODERNIZATION PROJECT $52,295.00
19486187
RUNWAY 10C-28C EAST AND TAXIWAYS, SPEC. 69501 07/27/2011 OHARE MODERNIZATION PROJECT ($25,525.00)
19486188
RUNWAY 10C-28C EAST AND TAXIWAYS, SPEC. 69501 07/28/2011 OHARE MODERNIZATION PROJECT $8,312.50
1948619
RUNWAY 10C-28C EAST AND TAXIWAYS, SPEC. 69501 09/30/2009 OHARE MODERNIZATION PROJECT $295,034.00
RUNWAY 10C-28C EAST AND TAXIWAYS, SPEC. 69501 08/02/2011 OHARE MODERNIZATION PROJECT $150,000.00
19486191
RUNWAY 10C-28C EAST AND TAXIWAYS, SPEC. 69501 08/03/2011 OHARE MODERNIZATION PROJECT ($189,856.50)
19486192
RUNWAY 10C-28C EAST AND TAXIWAYS, SPEC. 69501 08/04/2011 OHARE MODERNIZATION PROJECT $136,735.60
RUNWAY 10C-28C EAST AND TAXIWAYS, SPEC. 69501 08/04/2011 OHARE MODERNIZATION PROJECT $150,000.00
RUNWAY 10C-28C EAST AND TAXIWAYS, SPEC. 69501 08/04/2011 OHARE MODERNIZATION PROJECT $302,000.00
RUNWAY 10C-28C EAST AND TAXIWAYS, SPEC. 69501 08/04/2011 OHARE MODERNIZATION PROJECT $22,300.00
19486196
RUNWAY 10C-28C EAST AND TAXIWAYS, SPEC. 69501 08/09/2011 OHARE MODERNIZATION PROJECT ($1,924,233.38)
RUNWAY 10C-28C EAST AND TAXIWAYS, SPEC. 69501 08/10/2011 OHARE MODERNIZATION PROJECT ($126,202.92)
19486198
RUNWAY 10C-28C EAST AND TAXIWAYS, SPEC. 69501 08/10/2011 OHARE MODERNIZATION PROJECT ($1,838,946.71)
RUNWAY 10C-28C EAST AND TAXIWAYS, SPEC. 69501 08/11/2011 OHARE MODERNIZATION PROJECT ($343,366.73)
194862
RUNWAY 10C-28C EAST AND TAXIWAYS, SPEC. 69501 05/18/2009 OHARE MODERNIZATION PROJECT ($46,007.00)
1948620
RUNWAY 10C-28C EAST AND TAXIWAYS, SPEC. 69501 10/08/2009 OHARE MODERNIZATION PROJECT $37,700.00
19486200
RUNWAY 10C-28C EAST AND TAXIWAYS, SPEC. 69501 08/11/2011 OHARE MODERNIZATION PROJECT ($221,178.99)
19486201
RUNWAY 10C-28C EAST AND TAXIWAYS, SPEC. 69501 08/11/2011 OHARE MODERNIZATION PROJECT ($417,849.95)
RUNWAY 10C-28C EAST AND TAXIWAYS, SPEC. 69501 08/12/2011 OHARE MODERNIZATION PROJECT $74,000.00
RUNWAY 10C-28C EAST AND TAXIWAYS, SPEC. 69501 08/12/2011 OHARE MODERNIZATION PROJECT $107,420.00
RUNWAY 10C-28C EAST AND TAXIWAYS, SPEC. 69501 08/12/2011 OHARE MODERNIZATION PROJECT $56,127.00
19486205
RUNWAY 10C-28C EAST AND TAXIWAYS, SPEC. 69501 08/15/2011 OHARE MODERNIZATION PROJECT ($1,494,280.00)
RUNWAY 10C-28C EAST AND TAXIWAYS, SPEC. 69501 08/16/2011 OHARE MODERNIZATION PROJECT ($94,506.00)
RUNWAY 10C-28C EAST AND TAXIWAYS, SPEC. 69501 08/16/2011 OHARE MODERNIZATION PROJECT $33,387.00
RUNWAY 10C-28C EAST AND TAXIWAYS, SPEC. 69501 08/17/2011 OHARE MODERNIZATION PROJECT $60,000.00
RUNWAY 10C-28C EAST AND TAXIWAYS, SPEC. 69501 08/17/2011 OHARE MODERNIZATION PROJECT ($141,690.33)
RUNWAY 10C-28C EAST AND TAXIWAYS, SPEC. 69501 11/14/2009 OHARE MODERNIZATION PROJECT $45,113.00
RUNWAY 10C-28C EAST AND TAXIWAYS, SPEC. 69501 08/18/2011 OHARE MODERNIZATION PROJECT $100,000.00
RUNWAY 10C-28C EAST AND TAXIWAYS, SPEC. 69501 08/18/2011 OHARE MODERNIZATION PROJECT $25,000.00
RUNWAY 10C-28C EAST AND TAXIWAYS, SPEC. 69501 08/18/2011 OHARE MODERNIZATION PROJECT $126,000.00
RUNWAY 10C-28C EAST AND TAXIWAYS, SPEC. 69501 08/18/2011 OHARE MODERNIZATION PROJECT $100,000.00
19486214
RUNWAY 10C-28C EAST AND TAXIWAYS, SPEC. 69501 08/19/2011 OHARE MODERNIZATION PROJECT $122,077.00
RUNWAY 10C-28C EAST AND TAXIWAYS, SPEC. 69501 08/19/2011 OHARE MODERNIZATION PROJECT $25,990.00
19486216
RUNWAY 10C-28C EAST AND TAXIWAYS, SPEC. 69501 08/23/2011 OHARE MODERNIZATION PROJECT ($80,296.43)
19486217
RUNWAY 10C-28C EAST AND TAXIWAYS, SPEC. 69501 10/21/2011 OHARE MODERNIZATION PROJECT ($2,332.95)
19486218
RUNWAY 10C-28C EAST AND TAXIWAYS, SPEC. 69501 10/26/2011 OHARE MODERNIZATION PROJECT ($3,416,255.00)
19486219
RUNWAY 10C-28C EAST AND TAXIWAYS, SPEC. 69501 10/27/2011 OHARE MODERNIZATION PROJECT ($78,769.75)
1948622
RUNWAY 10C-28C EAST AND TAXIWAYS, SPEC. 69501 11/23/2009 OHARE MODERNIZATION PROJECT $63,134.00
19486220
RUNWAY 10C-28C EAST AND TAXIWAYS, SPEC. 69501 11/03/2011 OHARE MODERNIZATION PROJECT $700.00
RUNWAY 10C-28C EAST AND TAXIWAYS, SPEC. 69501 11/23/2009 OHARE MODERNIZATION PROJECT $2,164,063.00
RUNWAY 10C-28C EAST AND TAXIWAYS, SPEC. 69501 11/25/2009 OHARE MODERNIZATION PROJECT $37,972.00
1948625
RUNWAY 10C-28C EAST AND TAXIWAYS, SPEC. 69501 12/02/2009 OHARE MODERNIZATION PROJECT ($350,000.00)
1948626
RUNWAY 10C-28C EAST AND TAXIWAYS, SPEC. 69501 12/02/2009 OHARE MODERNIZATION PROJECT $54,310.00
1948627
RUNWAY 10C-28C EAST AND TAXIWAYS, SPEC. 69501 12/07/2009 OHARE MODERNIZATION PROJECT ($34,012.00)
1948628
RUNWAY 10C-28C EAST AND TAXIWAYS, SPEC. 69501 12/09/2009 OHARE MODERNIZATION PROJECT $27,458.00
RUNWAY 10C-28C EAST AND TAXIWAYS, SPEC. 69501 12/11/2009 OHARE MODERNIZATION PROJECT ($41,755.70)
194863
RUNWAY 10C-28C EAST AND TAXIWAYS, SPEC. 69501 05/20/2009 OHARE MODERNIZATION PROJECT ($600,600.00)
RUNWAY 10C-28C EAST AND TAXIWAYS, SPEC. 69501 12/14/2009 OHARE MODERNIZATION PROJECT $100,000.00
RUNWAY 10C-28C EAST AND TAXIWAYS, SPEC. 69501 12/15/2009 OHARE MODERNIZATION PROJECT $40,000.00
RUNWAY 10C-28C EAST AND TAXIWAYS, SPEC. 69501 12/21/2009 OHARE MODERNIZATION PROJECT ($20,921.02)
1948633
RUNWAY 10C-28C EAST AND TAXIWAYS, SPEC. 69501 12/22/2009 OHARE MODERNIZATION PROJECT ($1,205,000.00)
1948634
RUNWAY 10C-28C EAST AND TAXIWAYS, SPEC. 69501 12/23/2009 OHARE MODERNIZATION PROJECT $70,960.00
1948635
RUNWAY 10C-28C EAST AND TAXIWAYS, SPEC. 69501 12/28/2009 OHARE MODERNIZATION PROJECT ($290,100.00)
1948636
RUNWAY 10C-28C EAST AND TAXIWAYS, SPEC. 69501 01/07/2010 OHARE MODERNIZATION PROJECT ($137,000.00)
1948637
RUNWAY 10C-28C EAST AND TAXIWAYS, SPEC. 69501 01/08/2010 OHARE MODERNIZATION PROJECT $698,939.50
1948638
RUNWAY 10C-28C EAST AND TAXIWAYS, SPEC. 69501 01/11/2010 OHARE MODERNIZATION PROJECT $128,125.00
1948639
RUNWAY 10C-28C EAST AND TAXIWAYS, SPEC. 69501 01/13/2010 OHARE MODERNIZATION PROJECT ($1,855,200.22)
194864
RUNWAY 10C-28C EAST AND TAXIWAYS, SPEC. 69501 05/27/2009 OHARE MODERNIZATION PROJECT $572,396.00
1948640
RUNWAY 10C-28C EAST AND TAXIWAYS, SPEC. 69501 01/13/2010 OHARE MODERNIZATION PROJECT ($2,019,586.00)
RUNWAY 10C-28C EAST AND TAXIWAYS, SPEC. 69501 01/15/2010 OHARE MODERNIZATION PROJECT $51,150.00
RUNWAY 10C-28C EAST AND TAXIWAYS, SPEC. 69501 01/19/2010 OHARE MODERNIZATION PROJECT ($46,706.82)
RUNWAY 10C-28C EAST AND TAXIWAYS, SPEC. 69501 01/21/2010 OHARE MODERNIZATION PROJECT ($15,470.81)
RUNWAY 10C-28C EAST AND TAXIWAYS, SPEC. 69501 01/22/2010 OHARE MODERNIZATION PROJECT ($76,251.05)
RUNWAY 10C-28C EAST AND TAXIWAYS, SPEC. 69501 01/25/2010 OHARE MODERNIZATION PROJECT $193,900.00
RUNWAY 10C-28C EAST AND TAXIWAYS, SPEC. 69501 01/26/2010 OHARE MODERNIZATION PROJECT $200,000.00
RUNWAY 10C-28C EAST AND TAXIWAYS, SPEC. 69501 01/27/2010 OHARE MODERNIZATION PROJECT $954,320.00
RUNWAY 10C-28C EAST AND TAXIWAYS, SPEC. 69501 01/29/2010 OHARE MODERNIZATION PROJECT ($66,915.00)
RUNWAY 10C-28C EAST AND TAXIWAYS, SPEC. 69501 02/01/2010 OHARE MODERNIZATION PROJECT $41,118.80
194865
RUNWAY 10C-28C EAST AND TAXIWAYS, SPEC. 69501 06/01/2009 OHARE MODERNIZATION PROJECT $115,267.70
1948650
RUNWAY 10C-28C EAST AND TAXIWAYS, SPEC. 69501 02/02/2010 OHARE MODERNIZATION PROJECT $378,820.00
1948651
RUNWAY 10C-28C EAST AND TAXIWAYS, SPEC. 69501 02/03/2010 OHARE MODERNIZATION PROJECT $155,575.00
RUNWAY 10C-28C EAST AND TAXIWAYS, SPEC. 69501 02/05/2010 OHARE MODERNIZATION PROJECT $113,000.00
RUNWAY 10C-28C EAST AND TAXIWAYS, SPEC. 69501 02/08/2010 OHARE MODERNIZATION PROJECT $19,000.00
RUNWAY 10C-28C EAST AND TAXIWAYS, SPEC. 69501 02/09/2010 OHARE MODERNIZATION PROJECT $15,000.00
RUNWAY 10C-28C EAST AND TAXIWAYS, SPEC. 69501 02/10/2010 OHARE MODERNIZATION PROJECT $37,500.00
RUNWAY 10C-28C EAST AND TAXIWAYS, SPEC. 69501 02/10/2010 OHARE MODERNIZATION PROJECT $680,000.00
RUNWAY 10C-28C EAST AND TAXIWAYS, SPEC. 69501 02/16/2010 OHARE MODERNIZATION PROJECT $33,000.00
RUNWAY 10C-28C EAST AND TAXIWAYS, SPEC. 69501 02/17/2010 OHARE MODERNIZATION PROJECT $358,708.00
RUNWAY 10C-28C EAST AND TAXIWAYS, SPEC. 69501 02/22/2010 OHARE MODERNIZATION PROJECT ($21,492.13)
194866
RUNWAY 10C-28C EAST AND TAXIWAYS, SPEC. 69501 06/04/2009 OHARE MODERNIZATION PROJECT ($182,638.19)
1948660
RUNWAY 10C-28C EAST AND TAXIWAYS, SPEC. 69501 02/24/2010 OHARE MODERNIZATION PROJECT ($61,656.15)
RUNWAY 10C-28C EAST AND TAXIWAYS, SPEC. 69501 02/24/2010 OHARE MODERNIZATION PROJECT ($4,544.92)
1948662
RUNWAY 10C-28C EAST AND TAXIWAYS, SPEC. 69501 02/24/2010 OHARE MODERNIZATION PROJECT $129,000.00
RUNWAY 10C-28C EAST AND TAXIWAYS, SPEC. 69501 02/28/2010 OHARE MODERNIZATION PROJECT ($235,470.00)
1948664
RUNWAY 10C-28C EAST AND TAXIWAYS, SPEC. 69501 03/05/2010 OHARE MODERNIZATION PROJECT ($145,810.00)
1948665
RUNWAY 10C-28C EAST AND TAXIWAYS, SPEC. 69501 03/09/2010 OHARE MODERNIZATION PROJECT $13,000.00
RUNWAY 10C-28C EAST AND TAXIWAYS, SPEC. 69501 03/10/2010 OHARE MODERNIZATION PROJECT $59,250.00
RUNWAY 10C-28C EAST AND TAXIWAYS, SPEC. 69501 03/15/2010 OHARE MODERNIZATION PROJECT $164,450.00
RUNWAY 10C-28C EAST AND TAXIWAYS, SPEC. 69501 03/16/2010 OHARE MODERNIZATION PROJECT $8,050.00
RUNWAY 10C-28C EAST AND TAXIWAYS, SPEC. 69501 03/22/2010 OHARE MODERNIZATION PROJECT ($125.92)
RUNWAY 10C-28C EAST AND TAXIWAYS, SPEC. 69501 06/10/2009 OHARE MODERNIZATION PROJECT $50,000.00
RUNWAY 10C-28C EAST AND TAXIWAYS, SPEC. 69501 03/23/2010 OHARE MODERNIZATION PROJECT ($6,822.82)
RUNWAY 10C-28C EAST AND TAXIWAYS, SPEC. 69501 03/26/2010 OHARE MODERNIZATION PROJECT $12,500.00
RUNWAY 10C-28C EAST AND TAXIWAYS, SPEC. 69501 03/31/2010 OHARE MODERNIZATION PROJECT ($50,005.40)
RUNWAY 10C-28C EAST AND TAXIWAYS, SPEC. 69501 04/06/2010 OHARE MODERNIZATION PROJECT $32,441.00
RUNWAY 10C-28C EAST AND TAXIWAYS, SPEC. 69501 04/07/2010 OHARE MODERNIZATION PROJECT $250,000.00
RUNWAY 10C-28C EAST AND TAXIWAYS, SPEC. 69501 04/08/2010 OHARE MODERNIZATION PROJECT $18,905.00
RUNWAY 10C-28C EAST AND TAXIWAYS, SPEC. 69501 04/16/2010 OHARE MODERNIZATION PROJECT ($50,000.00)
1948677
RUNWAY 10C-28C EAST AND TAXIWAYS, SPEC. 69501 04/19/2010 OHARE MODERNIZATION PROJECT $13,520.00
RUNWAY 10C-28C EAST AND TAXIWAYS, SPEC. 69501 04/19/2010 OHARE MODERNIZATION PROJECT ($144,126.83)
RUNWAY 10C-28C EAST AND TAXIWAYS, SPEC. 69501 04/20/2010 OHARE MODERNIZATION PROJECT ($1,625.00)
RUNWAY 10C-28C EAST AND TAXIWAYS, SPEC. 69501 06/15/2009 OHARE MODERNIZATION PROJECT $100,010.00
RUNWAY 10C-28C EAST AND TAXIWAYS, SPEC. 69501 04/21/2010 OHARE MODERNIZATION PROJECT $46,175.00
RUNWAY 10C-28C EAST AND TAXIWAYS, SPEC. 69501 04/28/2010 OHARE MODERNIZATION PROJECT $10,726.00
1948682
RUNWAY 10C-28C EAST AND TAXIWAYS, SPEC. 69501 05/12/2010 OHARE MODERNIZATION PROJECT $211,064.49
RUNWAY 10C-28C EAST AND TAXIWAYS, SPEC. 69501 05/17/2010 OHARE MODERNIZATION PROJECT $5,249.00
RUNWAY 10C-28C EAST AND TAXIWAYS, SPEC. 69501 05/21/2010 OHARE MODERNIZATION PROJECT $18,194.00
1948685
RUNWAY 10C-28C EAST AND TAXIWAYS, SPEC. 69501 05/25/2010 OHARE MODERNIZATION PROJECT ($600,000.00)
RUNWAY 10C-28C EAST AND TAXIWAYS, SPEC. 69501 06/01/2010 OHARE MODERNIZATION PROJECT $202,693.00
RUNWAY 10C-28C EAST AND TAXIWAYS, SPEC. 69501 06/09/2010 OHARE MODERNIZATION PROJECT $1,021,308.00
RUNWAY 10C-28C EAST AND TAXIWAYS, SPEC. 69501 06/09/2010 OHARE MODERNIZATION PROJECT $63,750.00
RUNWAY 10C-28C EAST AND TAXIWAYS, SPEC. 69501 06/11/2010 OHARE MODERNIZATION PROJECT ($60,000.00)
RUNWAY 10C-28C EAST AND TAXIWAYS, SPEC. 69501 06/19/2009 OHARE MODERNIZATION PROJECT $100,000.00
RUNWAY 10C-28C EAST AND TAXIWAYS, SPEC. 69501 06/16/2010 OHARE MODERNIZATION PROJECT ($789,180.00)
RUNWAY 10C-28C EAST AND TAXIWAYS, SPEC. 69501 06/17/2010 OHARE MODERNIZATION PROJECT ($8,236.47)
RUNWAY 10C-28C EAST AND TAXIWAYS, SPEC. 69501 06/22/2010 OHARE MODERNIZATION PROJECT ($6,767.36)
RUNWAY 10C-28C EAST AND TAXIWAYS, SPEC. 69501 06/23/2010 OHARE MODERNIZATION PROJECT ($2,488.00)
RUNWAY 10C-28C EAST AND TAXIWAYS, SPEC. 69501 06/28/2010 OHARE MODERNIZATION PROJECT ($4,359.92)
RUNWAY 10C-28C EAST AND TAXIWAYS, SPEC. 69501 06/29/2010 OHARE MODERNIZATION PROJECT ($25,538.73)
RUNWAY 10C-28C EAST AND TAXIWAYS, SPEC. 69501 07/08/2010 OHARE MODERNIZATION PROJECT $11,227.60
RUNWAY 10C-28C EAST AND TAXIWAYS, SPEC. 69501 07/13/2010 OHARE MODERNIZATION PROJECT $17,427.19
RUNWAY 10C-28C EAST AND TAXIWAYS, SPEC. 69501 07/15/2010 OHARE MODERNIZATION PROJECT $6,407.05
1948699
RUNWAY 10C-28C EAST AND TAXIWAYS, SPEC. 69501 07/19/2010 OHARE MODERNIZATION PROJECT $1,372,383.55