| Modification # | Description | Disclosure # | Award Date | Start Date | End Date | Department | Amount |
|---|---|---|---|---|---|---|---|
| 1183156: SEWER MAIN LINING PROGRAM - FAR SOUTH AREA (Project#7511E) | 11/22/2022 | 08/12/2020 | 12/21/2023 | DEPARTMENT OF WATER MANAGEMENT | $1,000,000.00 | ||
| 1183156: SEWER MAIN LINING PROGRAM - FAR SOUTH AREA (Project#7511E) | 02/23/2024 | 08/12/2020 | 07/31/2024 | DEPARTMENT OF WATER MANAGEMENT | DUR | ||
|
1326363
| 1183156: SEWER MAIN LINING PROGRAM - FAR SOUTH AREA (Project#7511E) | 11/08/2024 | 08/12/2020 | 03/31/2025 | DEPARTMENT OF WATER MANAGEMENT | DUR | |
| 1183156: SEWER MAIN LINING PROGRAM - FAR SOUTH AREA (Project#7511E) | 04/10/2025 | 08/12/2020 | 10/31/2025 | DEPARTMENT OF WATER MANAGEMENT | DUR | ||
| 1183156: SEWER MAIN LINING PROGRAM - FAR SOUTH AREA (Project#7511E) | 01/20/2026 | 08/12/2020 | 05/31/2026 | DEPARTMENT OF WATER MANAGEMENT | $1,437,811.94 |